A company estimates that its weighted average cost of capital is 10 percent. Whi
ID: 2630506 • Letter: A
Question
A company estimates that its weighted average cost of capital is 10 percent. Which of the following independent projects should the company accept?
A. Project A requires an up-front expenditure of $1,000,000 and generates a net present value of $3,200.
B. Project B has a payback period of 12 years.
C. roject C requires an up-front expenditure of $1,000,000 and generates a positive internal rate of return of 9.7 percent.
D. Project D has an internal rate of return of 9.5 percent
E. None of the projects above should be accepted.
Explanation / Answer
A. Project A requires an up-front expenditure of $1,000,000 and generates a net present value of $3,200.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.