Calculate the MIRR of the project using the discounting approach method. (Do not
ID: 2633278 • Letter: C
Question
Calculate the MIRR of the project using the discounting approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
Calculate the MIRR of the project using the reinvestment approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
Calculate the MIRR of the project using the combination approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
Slow Ride Corp. is evaluating a project with the following cash flows:
Explanation / Answer
(a) MIRR using the discounting approach. MIRR ______ Percent Solution: Computation of the MIRR Initial investment investment $ (29,100.00) Cash flow $ (5,390.56) $ (34,490.56) Years Cash flows 0 $ (34,491) 1 $ 11,300 2 $ 14,000 3 $ 15,900 4 $ 13,000 MIRR = 20.18% Hence the MIRR is 20.18% (b) MIRR using the reinvestment approach. MIRR ______ Percent Solution Computation of the Reinvestment approach Cash flow Reinvested rate Total cash flows $ 11,300 1.31079601 $ 14,811.99 $ 14,000 1.225043 $ 17,150.60 $ 15,900 1.1449 $ 18,203.91 $ 13,000 1.07 $ 13,910.00 $ (9,500) 1 $ (9,500.00) $ 54,576.51 -29100+ $ 54,576.51 (1+MIRR)^5 $ 1.88 (1+MIRR)^5 1.134024792 (1+MIRR) MIRR = 0.134024792 MIRR = 13.40% Hence the MIRR is 13.40% (c) MIRR using the combination approach. MIRR ______ percent Solution Computation of the Combination approach Initial investment investment $ (29,100.00) Cash flow $ (5,390.56) $ (34,490.56) Cash flow Reinvested rate Total cash flows $ 11,300 1.31079601 $ 14,811.99 $ 14,000 1.225043 $ 17,150.60 $ 15,900 1.1449 $ 18,203.91 $ 13,000 1.07 $ 13,910.00 $ 64,076.51 $ (34,490.56) $ 64,076.51 (1+MIRR)^5 $ 1.86 (1+MIRR)^5 1.131878255 (1+MIRR) MIRR = 0.131878255 MIRR = 13.19% Hence the MIRR is 13.19%
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.