Purple Haze Machine Shop is considering a four-year project to improve its produ
ID: 2633593 • Letter: P
Question
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $460,000 is estimated to result in $185,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $78,000. The press also requires an initial investment in spare parts inventory of $19,000, along with an additional $2,400 in inventory for each succeeding year of the project. The shop
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $460,000 is estimated to result in $185,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $78,000. The press also requires an initial investment in spare parts inventory of $19,000, along with an additional $2,400 in inventory for each succeeding year of the project. The shop
Explanation / Answer
First, we will calculate the depreciation each year, which will be:
D1 = $460,000*(0.2000) = $92,000
D2 = $460,000*(0.3200) = $147200
D3 = $460,000*(0.1920) = $88320
D4 = $460,000*(0.1152) = $52992
The book value of the equipment at the end of the project is:
BV4 = $460000-(92000+147200+88320+52992) = $79488
The asset is sold at a loss to book value, so this creates a tax refund.
After-tax salvage value = $78000+(79488-78000)(0.34) = $78505.92
OCF1 = $185000(1-34%)+0.34(92000) = $153380
OCF2 = $185000(1-34%)+0.34(147200) = $172148
OCF3 = $185000(1-34%)+0.34(88320) = $152128.80
OCF4 = $185000(1-34%)+0.34(52992) = $140117.28
We need to be careful with the NWC in this project. Notice the project requires $19,000 of NWC at the beginning, and $2400 more in NWC each successive year.
We will subtract the $19,000 from the initial cash flow, and subtract $2400 each year from the OCF to account for this spending.
In Year 4, we will add back the total spent on NWC, which is $26200
NPV:
hence, $78253.15 is the NPV
Year Cashflows Present value 0 -479000 -479000 1 150980 137254.55 2 169748 140287.60 3 149728.8 112493.46 4 244823.2 167217.54 NPV 78253.15Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.