Nicholson roofing materials, inc., is considering two mutually exclusive project
ID: 2636174 • Letter: N
Question
Nicholson roofing materials, inc., is considering two mutually exclusive projects., each with an initial investment of $150,000. The company's board of directors has set a maximum 4-year payback requirement and has set its cost of capital at 9%. The cash inflows associated with the two projects are shown in the following table
a. Calculate the payback period for each project.
b. Calculate the NPV of each project at 0%
c. Calculate the NPV of each project at 9%
d. Derive the IRR of each project.
e. Rank the projects by each of hte techniques used. Make and justify a recommendation.
F. Go back one more time and calculate the NPV of each prject using a cost of capital of 12%. Does the ranking of the two projects change compared ot your answer in part e? Why?
Please show work in Excel.
Year Project A Project B 1 45000 75000 2 45000 60000 3 45000 30000 4 45000 30000 5 45000 30000 6 45000 30000Explanation / Answer
Project A :
In 3 years 45,000 * 3 = $ 135,000 is the total inflow.
So,the balance 150,000 - 135,000 = $ 15,000 will be recovered in the fourth year.
Now, we can see that 45,000 is earned in 12 months
Hence, to earn 15,000 time required : 12/45,000 * 15,000 = 4 months (Approx)
So, the payback period for Project A is 3 years and 4 months.
Project B :
In 2 years 75,000 + 60,000 = $ 135,000 is the Inflow.
So, the balance 150,000 - 135,000 = $ 15,000 was recovered in 3rd year.
The inflow for 3rd year was 30,000 which was in 12 months
So, for 15,000 they required 6 months
Hence, the payback period of Project B is 2 years and 6 months.
NPV at 0 % :
NPV of Project A : 270,000 - 150,000 = $ 120,000
NPV of Project B : 255,000 - 150,000 = $ 105,000
NPV when COC is 9 % : Project A
Inflow/(1 + 9/100)n
n = no of years
45,000/(1 + .09)1
45,000/(1 + .09)2
45,000/(1 + .09)3
45,000/(1 + .09)4
45,000/(1 + .09)5
45,000/(1 + .09)6
Hence NPV of Project B at 9 % COC is 204,240 - 150,000 = $ 54,240
Project B :
75,000/(1 + .09)1
60,000/(1 + .09)2
30,000/(1 + .09)3
30,000/(1 + .09)4
30,000/(1 + .09)5
30,000/(1 + .09)6
So, NPV of Project B is 201,114 - 150,000 = $ 51,114
IRR for Project A :
-150,000 + 45,000/(1 + 9/100)1 + 45,000/(1 + 9/100)2 + 45,000/(1 + 9/100)3 + 45,000/(1 + 9/100)4 + 45,000/(1 + 9/100)5 + 45,000/(1 + 9/100)6
Putting the values in IRR calculator we get 19.91 %
IRR for Project B :
-150,000 + 75,000/(1 + 9/100)1 + 60,000/(1 + 9/100)2 + 30,000/(1 + 9/100)3 + 30,000/(1 + 9/100)4 + 30,000/(1 + 9/100)5 + 30,000/(1 + 9/100)6
Putting the values in IRR calculator we get 22.72 %
Project B is more profitable as it be seen from the calculations.IRR of Project B is much higher as compared to Project A.Also, the payback period of Project B is lower so it must be given the priority.
NPV at COC 12 % : Project A
Inflow/(1 + 12/100)n
45,000/(1 + .12)1
45,000/(1 + .12)2
45,000/(1 + .12)3
45,000/(1 + .12)4
45,000/(1 + .12)6
Hence NPV will be 185,006 - 150,000 = 35,006
NPV at COC 12 % : Project B
75,000/(1 + .12)1
60,000/(1 + .12)2
30,000/(1 + .12)3
30,000/(1 + .12)4
30,000/(1 + .12)5
30,000/(1 + .12)6
So, NPV for Project B will be 187,432 - 150,000 = $ 37,432
The management should give the priorith to Project B.The payback period i.e. BEP is less also IRR is higher to Project A.NPV is also considerably good.
Year Project A ($) Project B ($) I 45,000 75,000 II 45,000 60,000 III 45,000 30,000 IV 45,000 30,000 V 45,000 30,000 VI 45,000 30,000 Total 270,000 255,000Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.