show all work WIT Facilities expects to incur dollar200,000 in overhead costs th
ID: 2642738 • Letter: S
Question
show all work
Explanation / Answer
Solution-a
The plantwide rate is calculated as follows:
Predetermined overhead rate=Estimated overhead costs/Estimated activity in allocation base
Predetermined overhead rate=$800,000/$160,000=$5 per $1 in direct labor cost (or 500 percent of direct labor cost)
Solution-b
The department rates are calculated using the same formula as the plantwide rate. However, overhead costs and activity levels are estimated for each department rather than for the entire company, and two separate rates are calculated:
Snow Removal department=$200,000/25,000 machine hours=$8 per machine hour
Quality Control department=$600,000/50,000 direct labor hours=$12 per direct labor hour
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.