Project S has a cost of $9,000 and is expected to produce benefits (cash flows)
ID: 2645072 • Letter: P
Question
Project S has a cost of $9,000 and is expected to produce benefits (cash flows) of $2,700 per year for 5 years. Project L costs $26,000 and is expected to produce cash flows of $7,100 per year for 5 years.
a. Calculate the two projects' NPVs, assuming a cost of capital of 10%. Round your answers to the nearest cent.
project S $
Project L $
Which project would be selected, assuming they are mutually exclusive?
b. Calculate the two projects' IRRs. Round your answers to two decimal places.
project S %
project L %
Which project would be selected, assuming they are mutually exclusive?
C.Calculate the two projects' MIRRs, assuming a cost of capital of 10%. Round your answers to two decimal places.
project s %
project L %
Which project would be selected, assuming they are mutually exclusive?
Calculate the two projects' PIs, assuming a cost of capital of 10%. Round your answers to two decimal places.
Project S
Project L
Which project would be selected, assuming they are mutually exclusive?
Which project should actually be selected?
Explanation / Answer
Answer to question a.
Project S
Project S to be chosen.
Answer to question b.
Project S = 15.25% approx
Project L = 11.50% approx
Project S to be chosen for higher IRR.
Answer to question c.
Project S = 35.33%
Project L = 22.39%
Project S to be chosen.
Answer to question d.
PI = Total cash inflow / cash outflow
Project S = 1.12
Project L = 1.04
Project S tp be chosen.
Year Cash Outflow Cash Inflow PV Factor PV 1 $ 9,000.00 $ 2,700.00 1.10 $ 2,454.55 2 $ - $ 2,700.00 1.10^2 $ 2,231.40 3 $ - $ 2,700.00 1.10^3 $ 2,028.55 4 $ - $ 2,700.00 1.10^4 $ 1,844.14 5 $ - $ 2,700.00 1.10^5 $ 1,676.49 $ 9,000.00 $ 10,235.12 NPV = $ 1,235.12 Project L Year Cash Outflow Cash Inflow PV Factor PV 1 $ 26,000.00 $ 7,100.00 1.10 $ 6,454.55 2 $ - $ 7,100.00 1.10^2 $ 5,867.77 3 $ - $ 7,100.00 1.10^3 $ 5,334.34 4 $ - $ 7,100.00 1.10^4 $ 4,849.40 5 $ - $ 7,100.00 1.10^5 $ 4,408.54 $ 26,000.00 $ 26,914.59 NPV = $ 914.59Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.