Organize the data into two options to evaluate. 1. Option 1 : Old Mover plus buy
ID: 2648364 • Letter: O
Question
Organize the data into two options to evaluate. 1. Option 1: Old Mover plus buying New Mover. Create a CFD for this option. 2. Option 2: Old Mover plus building Conveyor System. Create a CFD for this option. Compute the Equivalent Uniform Annual Worth (EUAW) for each option and then compare to select the least costly option. Please note that both options are considered defenders since they both retain the old mover and as such you need to use the Opportunity Cost approach for both options. A concrete company currently ovrns an earth mover to transport ran material from the quarry to the crushers. Due to increased construction activity, the company needs to increase its capacity to 400,000 metric tons per year. The company is considering two options: Keeping its old mover plus buying a new mover. Keeping its old mover and building a conveyor system. If the movers alone are used, the distance to the crusher is kilometers. If the convey or is built the distance is reduced to kilometer. Using the data below and employ ing the "Opportunity Cost" replacement analysis, when appropriate, determine the EUAW of the least cost option.Explanation / Answer
If Movers Used=Annual Cost=.01*180000*2.4*=4320
additional capacity required=400000-180000=220000
Cost=.01*220000*2.4=5280
Conveyer=400000-180000=220000
=220000*.0075*.32=528
Old Mover=180000*.32*.01=576
New Mover
Conveyer
Old Mover 16630
Conveyer 17415
If Conver is used Decrease in operating cost=(4320-576)4.56=17073
aNNNUAL=17073/4.56=3744
iF CONVEYER IS USED Annual Cash Flow=17415-3744=13671
Profit in Net Cash ouflow=16630-13671=2959
Hence Option II is better i.e. keeping the old mover and building conveyar
Outflow 70000 1 70000 Annual Operating Cost 5280 5.94 31363 Salvage Value 8000 .321 (2576) Total 98787 EAW 98787/5.94 =16630Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.