Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

3 investments compared over a ten year study period. only invest if you can earn

ID: 2649409 • Letter: 3

Question

3 investments compared over a ten year study period. only invest if you can earn more than 8% interest (nominal)

1) intial cost 50000 earn 12000 yearly OandM cost is 4600/ year

2)750000 initial net earnings 175000 and then an OandMcost of 60000 / year

this option has an IRR(internal rate of return) of 8.64%

3) 2000 intital 350 earning yearly and cost of 50 a year

Compute the IRR for the first option to 1/100th of a percent

if the projects are independent which ones should you invest in?

if the projects are exclusive and you have to choose which should you invest in (based on the IRR)

Explanation / Answer

Answer No. 1

Compute the IRR for the first option to 1/100th of a percent

IRR is discount rate that makes the net present value of all cash flows from a particular project equal to zero. To find out IRR We have to assume various discount rate by trial and error method.

Suppose discount rate is 7.8466%

Year

Cash outflow

Cash inflow

Net cash flow

Disc rate - 7.85%

present value

A

B

C

D

C*D

A+B

0

-50000

0

-50000

1.00

-50000

1

-4600

12000

7400

0.93

6862

2

-4600

12000

7400

0.86

6362

3

-4600

12000

7400

0.80

5899

4

-4600

12000

7400

0.74

5470

5

-4600

12000

7400

0.69

5072

6

-4600

12000

7400

0.64

4703

7

-4600

12000

7400

0.59

4361

8

-4600

12000

7400

0.55

4044

9

-4600

12000

7400

0.51

3750

10

-4600

12000

7400

0.47

3477

IRR

7.8466%

NPV

0.0

Answer : So IRR of project 1 is 7.85% (Approx)

Answer No. 2

if the projects are independent which ones should you invest in?

3 investments compared over a ten year study period. only invest if you can earn more than 8% interest (nominal).

So cost of capital is 8%.

Project 1

Year

Cash outflow

Cash inflow

Net cashflow

Disc Rate - 8%

Net cashflow

A

B

C

D

C*D

A+B

0

-50000

0

-50000

1.00

-50000

1

-4600

12000

7400

0.93

6851.85

2

-4600

12000

7400

0.86

6344.31

3

-4600

12000

7400

0.79

5874.36

4

-4600

12000

7400

0.74

5439.22

5

-4600

12000

7400

0.68

5036.32

6

-4600

12000

7400

0.63

4663.26

7

-4600

12000

7400

0.58

4317.83

8

-4600

12000

7400

0.54

3997.99

9

-4600

12000

7400

0.50

3701.84

10

-4600

12000

7400

0.46

3427.63

NPV

-345.40

Project 2

Year

Cash outflow

Cash inflow

Net cashflow

Disc Rate - 8%

Net cashflow

A

B

C

D

C*D

A+B

0

-750000

0

-750000

1.00

-750000

1

-60000

175000

115000

0.93

106481.48

2

-60000

175000

115000

0.86

98593.96

3

-60000

175000

115000

0.79

91290.71

4

-60000

175000

115000

0.74

84528.43

5

-60000

175000

115000

0.68

78267.07

6

-60000

175000

115000

0.63

72469.51

7

-60000

175000

115000

0.58

67101.40

8

-60000

175000

115000

0.54

62130.92

9

-60000

175000

115000

0.50

57528.63

10

-60000

175000

115000

0.46

53267.25

NPV

21659.36

Project 3

Year

Cash outflow

Cash inflow

Net cashflow

Disc Rate - 8%

Net cashflow

A

B

C

D

C*D

A+B

0

-2000

0

-2000

1.00

-2000

1

-50

350

300

0.93

277.78

2

-50

350

300

0.86

257.20

3

-50

350

300

0.79

238.15

4

-50

350

300

0.74

220.51

5

-50

350

300

0.68

204.17

6

-50

350

300

0.63

189.05

7

-50

350

300

0.58

175.05

8

-50

350

300

0.54

162.08

9

-50

350

300

0.50

150.07

10

-50

350

300

0.46

138.96

NPV

13.02

Answer :   NPV of Project 2 and Project 3 is positive. So Project 2 and Project 3 should be accepted.

Answer 3

if the projects are exclusive and you have to choose which should you invest in (based on the IRR)

IRR is discount rate that makes the net present value of all cash flows from a particular project equal to zero. To find out IRR We have to assume various discount rate by trial and error method.

Project 1

Suppose discount rate is 7.85%

Year

Cash outflow

Cash inflow

Net cash flow

A

B

C

A+B

0

-50000

0

-50000

1

-4600

12000

7400

2

-4600

12000

7400

3

-4600

12000

7400

4

-4600

12000

7400

5

-4600

12000

7400

6

-4600

12000

7400

7

-4600

12000

7400

8

-4600

12000

7400

9

-4600

12000

7400

10

-4600

12000

7400

IRR

7.85%

Project 2

Suppose discount rate is 8.64%

Year

Cash outflow

Cash inflow

Net cashflow

A

B

C

A+B

0

-750000

0

-750000

1

-60000

175000

115000

2

-60000

175000

115000

3

-60000

175000

115000

4

-60000

175000

115000

5

-60000

175000

115000

6

-60000

175000

115000

7

-60000

175000

115000

8

-60000

175000

115000

9

-60000

175000

115000

10

-60000

175000

115000

IRR

8.64%

Project 3

Suppose discount rate is 8.14%

Year

Cash outflow

Cash inflow

Net cash flow

A

B

C

A+B

0

-2000

0

-2000

1

-50

350

300

2

-50

350

300

3

-50

350

300

4

-50

350

300

5

-50

350

300

6

-50

350

300

7

-50

350

300

8

-50

350

300

9

-50

350

300

10

-50

350

300

IRR

8.14%

Answer : if the projects are exclusive , based on the IRR we should invest in project 2 because project 2 has highest IRR of 8.64% among all three projects.

Year

Cash outflow

Cash inflow

Net cash flow

Disc rate - 7.85%

present value

A

B

C

D

C*D

A+B

0

-50000

0

-50000

1.00

-50000

1

-4600

12000

7400

0.93

6862

2

-4600

12000

7400

0.86

6362

3

-4600

12000

7400

0.80

5899

4

-4600

12000

7400

0.74

5470

5

-4600

12000

7400

0.69

5072

6

-4600

12000

7400

0.64

4703

7

-4600

12000

7400

0.59

4361

8

-4600

12000

7400

0.55

4044

9

-4600

12000

7400

0.51

3750

10

-4600

12000

7400

0.47

3477

IRR

7.8466%

NPV

0.0