Calculate the MIRR of the project using the discounting approach method. (Do not
ID: 2650615 • Letter: C
Question
Calculate the MIRR of the project using the discounting approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
Calculate the MIRR of the project using the reinvestment approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
Calculate the MIRR of the project using the combination approach method. (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))
Slow Ride Corp. is evaluating a project with the following cash flows:
Explanation / Answer
MIRR using discounted cash flow method:
MIRR is the rate at which NPV is 0 by discounting cash outflow with the cost of capital and inflows are discounted using finanical cost.
By using the above concept MIRR = -29,200-9600/(1+.09)5
= -29,200 - $6,239.34
=- $35,439.34.
Let x be the MIRR
0=-35,439.34 +$11,400/(1+x)+$14,100/(1+x)2+16,000/(1+x)3+$13,100(1+x)4
Solving this equation for x would give the MIRR rate.
Formula for MIRR using the reinvestment method is as follows:
=nthroot(Future value of cash flows at cost of capital/Present value of cash outflow) -1
Terminal cash flows=$67,640.54 - $9,600
Terminal cash flows=$58,040.54
Substituting the values in the formula =5th root($58,040.54/29,200) -1
1.14728 -1 =14.73%.
Therefore MIRR using reinvestment method =14.73%
MIRR using combination approach:
In this approach the present value of cash outflows is calculated:
= -29,200-9600/(1+.09)5
= -29,200 - $6,239.34
=- $35,439.34.
Future value of cash inflows:
MIRR =5th root($67,640.54/$35,439.34)
MIRR =1.138005 -1 =13.80%
Therefore MIRR using combination approach =13.80%
Cash flows Future value factor Future value $11,400.00 1.411582 $16,092.03 $14,100.00 1.295029 $18,259.91 $16,000.00 1.1881 $19,009.60 $13,100.00 1.09 $14,279.00 Total $67,640.54Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.