Consider the following information given below: Calculate the NPV of the propose
ID: 2650661 • Letter: C
Question
Consider the following information given below:
Calculate the NPV of the proposed polyzone project, if spread in year 4 holds at $1.15 per pound. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.)
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5-10 Investment 100 Required rate of return 8% Production, millions of pounds per year 0 0 45 90 90 90 Spread, $ per pound 1.25 1.25 1.25 1.25 1.15 1.00 Production costs 0 0 35 35 35 35 Transport 0 0 9 10 10 10 Other costs 0 25 25 25 25 25
Explanation / Answer
Initial Investment = 100
since from Year 5-9 cash flows are same , We will use present value annuity factor from year 5 to year 10
NPV =present value of cash flows- initial investment
=92.240945-100
= (7.759055) or( 7.76 )
therefore project should not be accepted as NPV is negative.
Year 1 2 3 4 5-10 Total Revenue (A) - 56.25 [45*1.25] 112.50 [90*1.25] 103.50 [90*1.15] 90 [90*1] Less: Production cost 0 35 35 35 35 Transport 0 9 10 10 10 other cost 25 25 25 25 25 Total cost (B) 25 69 70 70 70 cash flow (A-B) (25) (12.75) 42.50 33.50 20 present value @ 8% [from Present value table .92593 .85734 .79383 .73503 3.39795** Present value of cash flows (23.14825) (10.931085) 33.737775 24.623505 67.959 92.240945Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.