Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider a project to supply Detroit with 40,000 tons of machine screws annually

ID: 2651611 • Letter: C

Question

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,400,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $450 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value of $380,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $560 per ton. The engineering department estimates you will need an initial net working capital investment of $540,000. You require a 12 percent return and face a marginal tax rate of 38 percent on this project.

   

Suppose you’re confident about your own projections, but you’re a little unsure about Detroit’s actual machine screw requirement. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))

   

What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))

   

Given the sensitivity number you calculated, what is the minimum level of output below which you wouldn’t want to operate? (Do not round intermediate calculations and round your final answer to the nearest whole number.)

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,400,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $450 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value of $380,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $560 per ton. The engineering department estimates you will need an initial net working capital investment of $540,000. You require a 12 percent return and face a marginal tax rate of 38 percent on this project.

Explanation / Answer

Answer

Base case NPV

Years

Quantity

Selling price

Variable cost

Contribution

Total contribution

Fixed cost

Profit

Salvage value

Depreciation tax benefit

Cost of investment

Working capital

Cashflow

Disc rate : 12%

Present value

per ton

per ton

Per ton

before tax

After tax

after tax

(Cost/ no of years) * tax rate

Salvage value( 1-tax rate)

A

B

C

D

E

F

G

H

I

J

K

L

M

N

B-C

A*D

E-F

G*(1-tax rate)

H+I+J+K+L

M*N

0

0

0

0

0

0

0

0

0

0

0

-5400000

-540000

-5940000

1

-5940000

1

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.89

2270535.71

2

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.80

2027264.03

3

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.71

1810057.17

4

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.64

1616122.47

5

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.57

1442966.49

6

40000

560

-450

110

4400000

-850000

3550000

2201000

235600

342000

0

540000

3318600

0.51

1681306.04

Net present value

4908251.92

a. Suppose you’re confident about your own projections, but you’re a little unsure about Detroit’s actual machine screw requirement. What is the sensitivity of the project OCF to changes in the quantity supplied?

OCF means Operating Cashflow. So initial cost of investment and its salvage value will not be taken.

Base case Operating NPV

Years

Quantity

Selling price

Variable cost

Contribution

Total contribution

Fixed cost

Profit

Salvage value

Depreciation tax benefit

Cost of investment

Working capital

Cashflow

Disc rate : 12%

Present value

per ton

per ton

Per ton

before tax

After tax

after tax

(Cost/ no of years) * tax rate

Salvage value( 1-tax rate)

A

B

C

D

E

F

G

H

I

J

K

L

M

N

B-C

A*D

E-F

G*(1-tax rate)

H+I+J+K+L

M*N

0

0

0

0

0

0

0

0

0

0

0

0

-540000

-540000

1

-540000

1

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.89

2270535.71

2

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.80

2027264.03

3

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.71

1810057.17

4

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.64

1616122.47

5

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.57

1442966.49

6

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

540000

3083000

0.51

1561943.75

Net present value of operating cashflow

10188889.63

Operating NPV if Quantity is reduced by 10%

Years

Quantity

Selling price

Variable cost

Contribution

Total contribution

Fixed cost

Profit

Salvage value

Depreciation tax benefit

Cost of investment

Working capital

Cashflow

Disc rate : 12%

Present value

per ton

per ton

Per ton

before tax

After tax

after tax

(Cost/ no of years) * tax rate

Salvage value( 1-tax rate)

A

B

C

D

E

F

G

H

I

J

K

L

M

N

B-C

A*D

E-F

G*(1-tax rate)

H+I+J+K+L

M*N

0

0

0

0

0

0

0

0

0

0

0

0

-540000

-540000

1

-540000

1

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.89

2026964.29

2

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.80

1809789.54

3

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.71

1615883.52

4

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.64

1442753.14

5

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.57

1288172.45

6

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

540000

2810200

0.51

1423734.78

Net present value of operating cashflow

9067297.71

Particulars

Amount

operating NPV if quantity is reduced by 10%

a

9067297.711

Base case Operating NPV

b

10188889.63

Change (a-b)

c

-1121591.92

operating NPV decrease in %      (c/b)*100

-11.01

b.     What is the sensitivity of NPV to changes in quantity supplied?

Suppose sales quantity is reduced by 10% i.e. 36000 tonnes ( 40000 tonnes * 0.9)

Years

Quantity

Selling price

Variable cost

Contribution

Total contribution

Fixed cost

Profit

Salvage value

Depreciation tax benefit

Cost of investment

Working capital

Cashflow

Disc rate : 12%

Present value

per ton

per ton

Per ton

before tax

After tax

after tax

(Cost/ no of years) * tax rate

Salvage value( 1-tax rate)

A

B

C

D

E

F

G

H

I

J

K

L

M

N

B-C

A*D

E-F

G*(1-tax rate)

H+I+J+K+L

M*N

0

0

0

0

0

0

0

0

0

0

0

-5400000

-540000

-5940000

1

-5940000

1

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.89

2026964.29

2

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.80

1809789.54

3

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.71

1615883.52

4

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.64

1442753.14

5

36000

560

-450

110

3960000

-850000

3110000

1928200

0

342000

0

0

2270200

0.57

1288172.45

6

36000

560

-450

110

3960000

-850000

3110000

1928200

235600

342000

0

540000

3045800

0.51

1543097.07

Net present value

3786660.00

Particulars

Amount

NPV if quantity is reduced by 10%

a

3786660.003

Base case NPV

b

4908251.92

Change (a-b)

c

-1121591.92

NPV decrease in %      (c/b)*100

-22.85

c. Given the sensitivity number you calculated, what is the minimum level of output below which you wouldn’t want to operate?

We wouldn’t operate if Project gives nagative NPV. So minimum NPV is zero.

Particulars

Amount

NPV

a

0

Base case NPV

b

4908251.92

Change (a-b)

c

-4908251.92

NPV decrease in %      (c/b)*100

d

-100.00

If NPV decrease in % (Answer b)

e

-22.85

then Quantity decrease in % (answer b)

f

10

Decrease in quantity in % when NPV is 0

43.76148

(d/e)*f

Quantity below which we won’t operate

22495.408

40000*(1-0.4376148)

Years

Quantity

Selling price

Variable cost

Contribution

Total contribution

Fixed cost

Profit

Salvage value

Depreciation tax benefit

Cost of investment

Working capital

Cashflow

Disc rate : 12%

Present value

per ton

per ton

Per ton

before tax

After tax

after tax

(Cost/ no of years) * tax rate

Salvage value( 1-tax rate)

A

B

C

D

E

F

G

H

I

J

K

L

M

N

B-C

A*D

E-F

G*(1-tax rate)

H+I+J+K+L

M*N

0

0

0

0

0

0

0

0

0

0

0

-5400000

-540000

-5940000

1

-5940000

1

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.89

2270535.71

2

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.80

2027264.03

3

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.71

1810057.17

4

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.64

1616122.47

5

40000

560

-450

110

4400000

-850000

3550000

2201000

0

342000

0

0

2543000

0.57

1442966.49

6

40000

560

-450

110

4400000

-850000

3550000

2201000

235600

342000

0

540000

3318600

0.51

1681306.04

Net present value

4908251.92

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote