Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Lang Industrial Systems Company (LISC) is trying to decide between two different

ID: 2653630 • Letter: L

Question

Lang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $256,000, has a four-year life, and requires $79,000 in pretax annual operating costs. System B costs $360,000, has a six-year life, and requires $73,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. Whichever project is chosen, it will not be replaced when it wears out. The tax rate is 35 percent and the discount rate is 10 percent.

Calculate the NPV for both conveyor belt systems.

NPV

  

Lang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $256,000, has a four-year life, and requires $79,000 in pretax annual operating costs. System B costs $360,000, has a six-year life, and requires $73,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. Whichever project is chosen, it will not be replaced when it wears out. The tax rate is 35 percent and the discount rate is 10 percent.

Explanation / Answer

Solution:

Computation of NPV

The information giben in trhe question doesnot specify, whether Operating costs are after depreciatioon or before Depreciation. therefore by both ways calculation of NPV is done.

1. Operating Costs are after Depreciation

Particulars

System A

System B

Initial Investment

256000

360000

Annual Operating costs pre-tax

79000

73000

After tax Annual Operating costs

51350

47450

Annual Depreciation

64000

60000

Cash inflow after adding Depreciation

12,650

12,550

PVAF @ 10 %

3.1698

4.355

Present Value of Cash inflows

40097.97

54655.25

NPV

= Present Value of Cash inflows - Initial Investment

= Present Value of Cash inflows - Initial Investment

= 40098 – 256000 = -215,902

= 54655 – 360000 = - 305,345

Decision, project with more NPV should be selected

This Project should be selected

This Project should not be selected

2. 1. Operating Costs are before Depreciation

Particulars

System A

System B

Initial Investment

256000

360000

Annual Operating costs pre-tax

79000 + 64,000 = 143,000

73000 + 60,000 = 133,000

After tax Annual Operating costs

= 92,950

= 86,450

Annual Depreciation

64000

60000

Cash outflow after adding Depreciation

= 28,950

= 26,450

PVAF @ 10 %

3.1698

4.355

Present Value of Cash outflows

91,766

115,190

NPV

= Present Value of Cash inflows - ( Initial Investment + Present Value of cash outflows )

= Present Value of Cash inflows - ( Initial Investment + Present Value of cash outflows )

= 0 – 256,000 + 91,766 = - $ 347,766

= 0 – 360000 + 115,190 = - $ 475,190

Decision, project with more NPV should be selected

This Project should be selected

This Project should not be selected

Particulars

System A

System B

Initial Investment

256000

360000

Annual Operating costs pre-tax

79000

73000

After tax Annual Operating costs

51350

47450

Annual Depreciation

64000

60000

Cash inflow after adding Depreciation

12,650

12,550

PVAF @ 10 %

3.1698

4.355

Present Value of Cash inflows

40097.97

54655.25

NPV

= Present Value of Cash inflows - Initial Investment

= Present Value of Cash inflows - Initial Investment

= 40098 – 256000 = -215,902

= 54655 – 360000 = - 305,345

Decision, project with more NPV should be selected

This Project should be selected

This Project should not be selected