2. You should accept both projects since both of their PIs are positive. You sho
ID: 2653880 • Letter: 2
Question
2.
You should accept both projects since both of their PIs are positive.
You should accept project A since it has the higher PI.
You should accept both projects since both of their PIs are greater than 1.
You should only accept project B since it has the largest PI and the PI exceeds 1.
Neither project is acceptable.
3.
Given the following information, calculate the present value break-even point.
Initial investment: $2,000
Fixed costs: $2,000 per year
Variable costs: $6 per unit
Depreciation: $250 per year
Price: $20 per unit
Discount rate: 10%
Project life: 4 years
Tax rate: 34%
100 units per year
143 units per year
202 units per year
286 units per year
None of these
4.
A 12-year, 5% coupon bond pays interest annually. The bond has a face value of $1,000. What is the change in the price of this bond if the market yield rises to 6% from the current yield of 4.5%?
11.11% decrease
12.38% decrease
12.38% increase
14.13% decrease
14.13% increase
5.
7.40%
8.25%
8.33%
9.45%
9.50%
6.
The following time period(s) is/are consistent with the bubble theory:
the stock market crash of 1929.
the stock market crash of 1972.
the stock market crash of 1987.
the stock market crash of 1929 and the stock market crash of 1987.
the stock market crash of 1929; the stock market crash of 1972; and the stock market crash of 1987.
Explanation / Answer
Answer:
1
Calculation of after tax cash flows
Sale value of the equipment (A)
$ 50,000.00
Less: Book value
$ (38,880.00)
225000*(100% -20%-32%-19.2%-11.52%)
Profit on Sale
$ 11,120.00
Tax on profit on sale @35% (B)
$ 3,892.00
After tax cash flows =A-B
$ 46,108.00
1
Calculation of after tax cash flows
Sale value of the equipment (A)
$ 50,000.00
Less: Book value
$ (38,880.00)
225000*(100% -20%-32%-19.2%-11.52%)
Profit on Sale
$ 11,120.00
Tax on profit on sale @35% (B)
$ 3,892.00
After tax cash flows =A-B
$ 46,108.00
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.