Modern Medical Mechanics (M3) chooses one major upgrade to implement in their production facility each year. The choice is made based only on the internal rate of return criterion. The forecasted cash flows for five alternatives are shown below. If M3 uses a MARR of 15%, which alternative should be selected? Investment in Year 0 1 2 3 A Pharmaceutical robots ($675,000) $280,000 $305,000 $360,000 B X-ray quality inspection ($950,000) $350,000 $400,000 $600,000 C Security System Upgrades ($575,000) $225,000 $250,000 $400,000 D Warehouse automation ($700,000) $275,000 $300,000 $350,000 E CNC lathe ($350,000) $100,000 $150,000 $250,000 Modern Medical Mechanics (M3) chooses one major upgrade to implement in their production facility each year. The choice is made based only on the internal rate of return criterion. The forecasted cash flows for five alternatives are shown below. If M3 uses a MARR of 15%, which alternative should be selected? Investment in Year 0 1 2 3 A Pharmaceutical robots ($675,000) $280,000 $305,000 $360,000 B X-ray quality inspection ($950,000) $350,000 $400,000 $600,000 C Security System Upgrades ($575,000) $225,000 $250,000 $400,000 D Warehouse automation ($700,000) $275,000 $300,000 $350,000 E CNC lathe ($350,000) $100,000 $150,000 $250,000Explanation / Answer
IRR is the discount rate at which PV of Cash Inflow is equal to PV of cash outflow
Using Excel formula
IRR = irr(values)
Pharmaceutical robots
IRR = irr({-675000,280000,305000,360000})
IRR = 18.04%
X-ray quality inspection
IRR = irr({-950000,350000,400000,600000})
IRR = 17.94%
Security System Upgrades
IRR = irr({-575000,225000,250000,400000})
IRR = 21.76%
Warehouse automation
IRR = irr({-700000,275000,300000,350000})
IRR = 14.68%
CNC lathe
IRR = irr({-350000,100000,150000,250000})
IRR = 17.17%
Decision : Security System Upgrades alternative should be selected as its IRR is higher among all alternative