Which one of the following will decrease the net present value of a project? Opt
ID: 2659152 • Letter: W
Question
Which one of the following will decrease the net present value of a project?
Options:
increasing the value of each of the project's discounted cash inflows
moving each of the cash inflows forward to a sooner time period
decreasing the required discount rate
increasing the project's initial cost at time zero
Which one of the following will decrease the net present value of a project? Options: increasing the value of each of the project's discounted cash inflows moving each of the cash inflows forward to a sooner time period decreasing the required discount rate increasing the project's initial cost at time zeroExplanation / Answer
Which one of the following will decrease the net present value of a project?
ANSWER:-OPTION-D:-INCREASING THE PROJECT
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.