\"\"\"\"\" Show work and email response to noworriestom@yahoo.com MS. Project /
ID: 2660777 • Letter: #
Question
""""" Show work and email response to noworriestom@yahoo.com MS. Project / Word Doc****
System Project. Using the complexity weighting scheme shown in Table 1 and the function point complexity weighted table (Table 2) shown below, estimate the total function point count. Assume historical data suggest five function points equal one person month and six people can work on the project.
Complexity Weight Table
Number of inputs
20
Rated complexity average
Number of outputs
10
Rated complexity low
Number of inquiries
10
Rated complexity low
Number of files
40
Rated complexity high
Number of interfaces
30
Rated complexity high
Table 1 Complexity Weighting Table
The total function point count is:
Complexity Weighting
Element
Count
Low
Average
High
Total
Inputs
20
20 x 4
=
80
Outputs
10
20 x 2
=
40
Inquiries
10
10 x 2
=
20
Files
40
40 x 12
=
480
Interfaces
30
30 x 15
=
450
TOTAL
=
1,070
Email response to noworriestom@yahoo.com for best answer please - Must show work in Project and Word Doc format
a. What is the estimated project duration?
b. If 20 people are available for the project, what is the estimated project duration?
c. If the project must be complete in six months, how many people will be needed for the project?
Complexity Weight Table
Number of inputs
20
Rated complexity average
Number of outputs
10
Rated complexity low
Number of inquiries
10
Rated complexity low
Number of files
40
Rated complexity high
Number of interfaces
30
Rated complexity high
Explanation / Answer
The estimated duration of the project would be 43 months. If there were 20 people available to work on the project it would cut the time down to about 13 months. If you would need the project within 6 months, you would need 43 people working on the project.