Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question: AST Company is attempting to select among the two mutuallyexclusive pr

ID: 2662183 • Letter: Q

Question

Question:
AST Company is attempting to select among the two mutuallyexclusive projects both of
which cost Rs. 100,000. The firm has a cost of capital equal to13%. After-tax cash
inflows associated with each project are shown in the followingtable :

Year        Project A(Rs.)                  Project B (Rs.)
1               40,000                                 45,000
2              25,000                                 25,000
3              35,000                                 20,000
4                5,000                                  20,000
5              20,000                                  20,000

REQUIRED :
(i) Calculate the Payback Period for each project. (2+3)
(ii) Calculate the Net Present Value (NPV) of each project.(5+5)
(iii) Calculate the Internal Rate of Return (IRR) for each project.(6+6)
(IRR must be calculated by using “Trial & Error Methodwith Interpolation
Formula”. IRR calculated directly by using Excel or FinancialCalculators, will
not be awarded full marks.)
(iv) Summarize and compare the above findings for both projects andindicate which
project you would recommend and why? (3) Question:
AST Company is attempting to select among the two mutuallyexclusive projects both of
which cost Rs. 100,000. The firm has a cost of capital equal to13%. After-tax cash
inflows associated with each project are shown in the followingtable :

Year        Project A(Rs.)                  Project B (Rs.)
1               40,000                                 45,000
2              25,000                                 25,000
3              35,000                                 20,000
4                5,000                                  20,000
5              20,000                                  20,000

REQUIRED :
(i) Calculate the Payback Period for each project. (2+3)
(ii) Calculate the Net Present Value (NPV) of each project.(5+5)
(iii) Calculate the Internal Rate of Return (IRR) for each project.(6+6)
(IRR must be calculated by using “Trial & Error Methodwith Interpolation
Formula”. IRR calculated directly by using Excel or FinancialCalculators, will
not be awarded full marks.)
(iv) Summarize and compare the above findings for both projects andindicate which
project you would recommend and why? (3)

Explanation / Answer

i) Calculate the Payback Period for eachproject.

Initial Investment = 100,000

Payback Period for Project A:

In year one, 40,000 will be covered, and (100,000-40,000) =60,000 should be covered.

In year two, further 25,000 will be covered, and (60,000-25,000)= 35,000 should be covered.

In year three, 35,000 will be covered, which we have to coverfrom the project.

So, our payback period is 3 years for ProjectA.

Payback Period for Project B:

In year one, 45,000 will be covered, and (100,000-45,000) =55,000 should be covered.

In year two, further 25,000 will be covered, and (55,000-25,000)= 30,000 should be covered.

In year three, 20,000 will be covered, and (30,000-20,000) =10,000 should be covered yet.

In year four, 20,000 will be covered, but we have to cover10,000 only,

So these 10,000 will take the time in years = 10,000/20,000 =0.5 years

OR 10,000 will take the time in months = 10,000/20,000 * 12 = 6months

OR 10,000 will take the time in days = 10,000/20,000 * 365 =182.5 days

So, payback period for Project B is 3.5 years, or 3years and 6 months or 3 years and 182.5 days.

ii) Calculate the Net Present Value (NPV) ofeach project.

NPV for Project A:

NPV = -Initial Investment + ? Cash Flows / (1+r)t

NPV = -100,000 + [40,000 / (1+0.13) 1] + [25,000 /(1+0.13) 2] + [35,000 / (1+0.13) 3] + [25,000/ (1+0.13) 4] + [20,000 / (1+0.13) 5]

NPV = -100,000 + [40,000 / (1.13) 1] + [25,000 /(1.13) 2] + [35,000 / (1.13) 3] + [25,000 /(1.13) 4] + [20,000 / (1.13) 5]

NPV = -100,000 + [40,000 / 1.13] + [25,000 / 1.2769] + [35,000 /1.442897] + [25,000 / 1.63047361] + [20,000 / 1.8424351793]

NPV = -100,000 + [35398.23] + [19578.67] + [24256.76] +[15332.97] + [10855.2]

NPV = 5421.83

NPV for Project B:

NPV = -Initial Investment + ? Cash Flows / (1+r)t

NPV = -100,000 + [45,000 / (1+0.13) 1] + [25,000 /(1+0.13) 2] + [20,000 / (1+0.13) 3] + [20,000/ (1+0.13) 4] + [20,000 / (1+0.13) 5]

NPV = -100,000 + [45,000 / (1.13) 1] + [25,000 /(1.13) 2] + [20,000 / (1.13) 3] + [20,000 /(1.13) 4] + [20,000 / (1.13) 5]

NPV = -100,000 + [45,000 / 1.13] + [25,000 / 1.2769] + [20,000 /1.442897] + [20,000 / 1.63047361] + [20,000 / 1.8424351793]

NPV = -100,000 + [39823] + [19578.67] + [13861] + [12266.37] +[10855.2]

NPV = -3615.76

iii) Calculate the Internal Rate of Return(IRR) for each project.

Internal rate of return (IRR) is a rate where, NPV becomes zerolet’s compute IRR for both projects,

We know the formula for Interpolation given as:

Rate1 + ((NPV1 / (NPV1 + NPV2)) * (Rate2 - Rate1))

But to apply this formula, we need another rate, where NPVshould be in opposite sign, so,

IRR for Project A:

Let’s take a rate of 16 percent, our NPV becomes:

NPV = -Initial Investment + ? Cash Flows / (1+r)t

NPV = -100,000 + [40,000 / (1+0.16) 1] + [25,000 /(1+0.16) 2] + [35,000 / (1+0.16) 3] + [25,000/ (1+0.16) 4] + [20,000 / (1+0.16) 5]

NPV = -100,000 + [40,000 / (1.16) 1] + [25,000 /(1.16) 2] + [35,000 / (1.16) 3] + [25,000 /(1.16) 4] + [20,000 / (1.16) 5]

NPV = -100,000 + [40,000 / 1.16] + [25,000 / 1.3456] + [35,000 /1.560896] + [25,000 / 1.81063936] + [20,000 / 2.1003416576]

NPV = -100,000 + [34482.76] + [18579.07] + [22423.02] +[13807.28] + [9522.26]

NPV = -1185.61

Applying Interpolation formula to get IRR:

Data:-

At 13%, NPV = 5421.83

At 16%, NPV = -1185.61

IRR = Rate1 + ((NPV1 / (NPV1 + NPV2)) * (Rate2 - Rate1))

IRR = 13% + ((5421.83 / (5421.83 + (1185.61))) * (16% -13%))

IRR = 13% + ((5421.83 / 6607.44) * (3))

IRR = 13% + ((0.8206) * (3))

IRR = 13% + (2.4618)

IRR = 15.46% approximately

IRR for Project B:

Let’s take a rate of 11 percent, our NPV becomes:

NPV = -Initial Investment + ? Cash Flows / (1+r)t

NPV = -100,000 + [45,000 / (1+0.11) 1] + [25,000 /(1+0.11) 2] + [20,000 / (1+0.11) 3] + [20,000/ (1+0.11) 4] + [20,000 / (1+0.11) 5]

NPV = -100,000 + [45,000 / (1.11) 1] + [25,000 /(1.11) 2] + [20,000 / (1.11) 3] + [20,000 /(1.11) 4] + [20,000 / (1.11) 5]

NPV = -100,000 + [45,000 / 1.11] + [25,000 / 1.2321] + [20,000 /1.367631] + [20,000 / 1.51807041] + [20,000 / 1.6850581551]

NPV = -100,000 + [40540.54] + [20290.56] + [14623.83] +[13174.62] + [11869.03]

NPV = 498.58

Applying Interpolation formula to get IRR:

Data:-

At 13%, NPV = -3615.76

At 11%, NPV = 498.58

IRR = Rate1 + ((NPV1 / (NPV1 + NPV2)) * (Rate2 - Rate1))

IRR = 11% + ((498.58 / (498.58 + (3615.76))) * (13% - 11%))

IRR = 11% + ((498.58 / 4114.34) * (2))

IRR = 11% + ((0.1212) * (2))

IRR = 11% + (0.2424)

IRR = 11.24% approximately

iv) Summarize and compare the above findings for both projectsand indicate which project you would recommend and why?

Answer:

                       Paybackperiod           NPV               IRR

Project A         3years                        5421.83          15.46%

Project B         3.5years                     -3615.76         11.24%

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote