Which of the following statements is CORRECT? Answer An example of a sunk cost i
ID: 2671846 • Letter: W
Question
Which of the following statements is CORRECT?Answer
An example of a sunk cost is the cost associated with restoring the site of a strip mine once the ore has been depleted.
Sunk costs must be considered if the IRR method is used but not if the firm relies on the NPV method.
A good example of a sunk cost is a situation where a bank opens a new office, and that new office leads to a decline in deposits of the bank's other offices.
A good example of a sunk cost is money that a banking corporation spent last year to investigate the site for a new office, then expensed that cost for tax purposes, and now is deciding whether to go forward with the project.
If sunk costs are considered and reflected in a project's cash flows, then the project's calculated NPV will be higher than it otherwise would be.
Explanation / Answer
A good example of a sunk cost is money that a banking corporation spent last year to investigate the site for a new office, then expensed that cost for tax purposes, and now is deciding whether to go forward with the project.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.