A mining company is considering a new project. Because the mine has received a p
ID: 2684310 • Letter: A
Question
A mining company is considering a new project. Because the mine has received a permit, the project would be legal; but it would cause significant harm to a nearby river. The firm could spend an additional $11 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. Developing the mine (without mitigation) would cost $69 million, and the expected net cash inflows would be $23 million per year for 5 years. If the firm does invest in mitigation, the annual inflows would be $24 million. The risk adjusted WACC is 11%. Calculate the NPV and IRR with mitigation. Round your answers to two decimal places. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. NPV $ million IRR % Calculate the NPV and IRR without mitigation. Round your answers to two decimal places. Enter your answer for NPV in millions. For example, an answer of $10,550,000 should be entered as 10.55. NPV $ million IRR %Explanation / Answer
with mitigation
NPV = -(69+11) +24(1/1.11 + 1/1.112 +....+1.115) = 8.70million
IRR
0 = -(69+11 ) + 24(1/r + 1/r2 +....+r5) r = 15.24%
without mitigation
NPV = -(69) +23(1/1.11 + 1/1.112 +....+1.115) = 16.01million
IRR = -(69) + 23(1/r + 1/r2 +....+r5) r = 19.86%
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.