Orlando International Airport plans to extend passenger capacity of its existing terminal to accommodate its forecasted growth. A new terminal would be needed once the state's busiest airport reached 40 million passengers annually. Based on current growth rates, Orlando International should reach the 40 million mark 11 years from now. The expansion cost is expected to be $400 million. The airport service areas will also need attention. These include passenger security checkpoints, ticketing lines, entering/exiting weaves, terminal ramps, baggage claim, and baggage handling. Improvements in these areas will cost an additional $240 million. How much does the airport need to set aside now to pay for these costs, if the company can earn 10% per year, compounded every 4 months.Explanation / Answer
A new terminal would be needed once the state's busiest airport reached 40 million passengers annually.
11 year time
expansion cost is expected to be $400 million
Improvements in these areas will cost an additional $240 million
r=10% per year, compounded every 4 months
let P be the value airport need to set aside now to pay for these costs
then
total cost in 11 yrs = 640 million
so
FV= PV*(1+r/3)^3*n
640=P*(1+0.1/3)^33
P= 216.89 million
please rate 5 Star for help and Explanation
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.