Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Start with the partial model in the file Ch10 P23 Build a Model.xls on the textb

ID: 2697884 • Letter: S

Question

Start with the partial model in the file Ch10 P23 Build a Model.xls on the textbook’ s

Web site. Gardial Fisheries is considering two mutually exclusive investments. The

projects’ expected net cash flows are as follows:

Expected Net Cash Flows

Year Project A Project B

0 −$375 −$575

1 −300 190

2 −200 190

3 −100 190

4 600 190

5 600 190

6 926 190

7 −200 0

a. If each project’ s cost of capital is 12%, which project should be selected? If the

cost of capital is 18%, what project is the proper choice?

b. Construct NPV profiles for Projects A and B.

c. What is each project’ s IRR?

d. What is the crossover rate, and what is its significance?

e. What is each project’ s MIRR at a cost of capital of 12%? At r = 18%?

(Hint: Consider Period 7 as the end of Project B’ s life.)

f. What is the regular payback period for these two projects?

g. At a cost of capital of 12%, what is the discounted payback period for these two

projects?

h. What is the profitability index for each project if the cost of capital

is 12%?

Explanation / Answer


1. NPV(A) = -200 + 80/(1.11) + 80/(1.11)^2 + 80/(1.11)^3 + 80/(1.11)^4 = 48.19
NPV(B) = -200 + 100/(1.11) + 100/(1.11)^2 + 100/(1.11)^3 = 44.37

both of the projects are feasible and worth pursuing.

2. If you have to select one, select the one with the higher NPV, so A

3. Repeat the calculations with 0.16 instead of 0.11
NPV(A) = 23.85
NPV(B) = 24.59
now you would choose B because it pays back faster and is more advantegous at a higher discount rate

4. IRR is the discount rate that makes the project break-even, i.e. solve for r such that NPV=0
IRR(A) = 21.86%
IRR(B) = 23.375%

5. Not necessarily, see that project A had a higher NPV when r=11% and project B had a higher NPV when r=16%. It doesn't only depend on IRR

6. PIR(A) = 48.19/200 = 24.1%
PIR(B) = 44.37/200 = 22.19%
Yes it does, because the initial investments are the same. (When initial investments are different, the project with higher NPV may be ranked later because it requires a higher initial investment.)

7. Payback period for A
2 + (200-160)/80 = 2.5 years
Payback period for B is exactly 2 years.
Payback period method advises you to choose the project with the shorter payback period.

8. No, because the payback period doesn't take the time value of money into account.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote