The following are the cash flows of two projects: Year Project A Project B 0 %u2
ID: 2699559 • Letter: T
Question
The following are the cash flows of two projects:Year Project A Project B 0 %u2212$350 %u2212$350 1 180 250 2 180 250 3 180 250 4 180
a. If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
Project Profitability Index A B
b. Does the profitability index rank the projects correctly? Yes No The following are the cash flows of two projects:
Explanation / Answer
for project A ...
NPV = -350 + 180 / 1.11 + 180/1.11^2 + 180/1.11^3 + 180/1.11^4 = 208.44
profitability index = 208.44 / 350 = 0.5955
for project B
NPV = -350 + 250/1.11 + 250 / 1.11^2 + 250 / 1.11 ^ 3 = 260.92867
Profitabiiyu inde x = 260.92867 / 350 = 0.7455
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.