ID: 2701903 • Letter: I
Question
I
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today.
What is the NPV for the project if the required return is 7 percent?
What is the NPV for the project if the required return is 19 percent?
At what discount rate would you be indifferent between accepting the project and rejecting it?
II
A project has the following cash flows:
What is the NPV at a discount rate of zero percent?
What is the NPV at a discount rate of 12 percent?
What is the NPV at a discount rate of 22 percent?
What is the NPV at a discount rate of 28 percent?
*I know how to do these but I cant find my calculator and it's due soon! It shouldn't take nothing more than inputting a few things in your caculator. Thanks!
I
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today.
What is the NPV for the project if the required return is 7 percent?
What is the NPV for the project if the required return is 19 percent?
At what discount rate would you be indifferent between accepting the project and rejecting it?
Explanation / Answer
NPV=21080.5030
NPV=-15425.9815
Discount rate=12.95%
2.NPV=7600
NPV=2668.463
NPV=-303.013
NPV=
-1741.2445Related Questions