The R&D dept. is planning to bid on a large project for the development of a new
ID: 2706366 • Letter: T
Question
The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, time & sequence required:
Activity
Immediate predecessor
Time (weeks)
A
---
3
B
A
2
C
A
4
D
A
4
E
B
6
F
C,D
6
G
D,F
2
H
D
3
I
E,G,H
3
A. Draw the Network Diagram
B. What is the critical path?
C. Suppose you want to shorten the completion time as much as possible, & you have the option of shortening any or all of B,C,D, and G each one week. Which would you shorten?
D. What is the new critical path & earliest completion time?
Please solve using Microsoft Excel & show any work if possible. Thanks!
Activity
Immediate predecessor
Time (weeks)
A
---
3
B
A
2
C
A
4
D
A
4
E
B
6
F
C,D
6
G
D,F
2
H
D
3
I
E,G,H
3
Explanation / Answer
A)
F
B
A
======================================================================================
B. What is the critical path?
. A-C-F-G-I, and A-D-F-G-I.
======================================================================================
c.
C: one week;
D: one week;
G: one week.
======================================================================================
D)
Two paths:
A-C-F-G-l and
A-D-F-G-I, 16 weeks