Frankies,LLC. is thinking about a project that has an initial after-tax outlay o
ID: 2707601 • Letter: F
Question
Frankies,LLC. is thinking about a project that has an initial after-tax outlay of $150,000. The relevant future cash inflows from its four-year project for years 1 through 4 are: $60,000, $70,000, $75,000 and $70,000. Frankies wants to base their decision using the net present value method and has a discount rate of 12%. Will Frankies accept the project?Frankies rejects the project because the NPV is about -$22,375.73.
Frankies rejects the project because the NPV is about -$2,375.60.
Frankies rejects the project because the NPV is about -$12,375.60.
Frankies accepts the project because the NPV is greater than $10,000.00.
Frankies,LLC. is thinking about a project that has an initial after-tax outlay of $150,000. The relevant future cash inflows from its four-year project for years 1 through 4 are: $60,000, $70,000, $75,000 and $70,000. Frankies wants to base their decision using the net present value method and has a discount rate of 12%. Will Frankies accept the project?
Frankies rejects the project because the NPV is about -$22,375.73.
Frankies rejects the project because the NPV is about -$2,375.60.
Frankies rejects the project because the NPV is about -$12,375.60.
Frankies accepts the project because the NPV is greater than $10,000.00.
Frankies,LLC. is thinking about a project that has an initial after-tax outlay of $150,000. The relevant future cash inflows from its four-year project for years 1 through 4 are: $60,000, $70,000, $75,000 and $70,000. Frankies wants to base their decision using the net present value method and has a discount rate of 12%. Will Frankies accept the project?
Frankies rejects the project because the NPV is about -$22,375.73.
Frankies rejects the project because the NPV is about -$2,375.60.
Frankies rejects the project because the NPV is about -$12,375.60.
Frankies accepts the project because the NPV is greater than $10,000.00.
Frankies rejects the project because the NPV is about -$22,375.73. Frankies rejects the project because the NPV is about -$2,375.60. Frankies rejects the project because the NPV is about -$12,375.60. Frankies accepts the project because the NPV is greater than $10,000.00. Frankies rejects the project because the NPV is about -$22,375.73.
Frankies rejects the project because the NPV is about -$2,375.60.
Frankies rejects the project because the NPV is about -$12,375.60.
Frankies accepts the project because the NPV is greater than $10,000.00.
Explanation / Answer
YEARS
CASHFLOWS
DISCOUNTING FACTOR
P.V @12%
0
(150000)
(150000)
1
60000
0.8929
53574
2
70000
0.7972
55804
3
75000
0.7118
53385
4
70000
0.6355
44485
NPV =
57248
SINCE NPV IS POSITIVETHE PROJECT IS NOT VIABLE AND THEREFORE SHOULD BE ACCEPTED
ANSWER :- OPTION
YEARS
CASHFLOWS
DISCOUNTING FACTOR
P.V @12%
0
(150000)
(150000)
1
60000
0.8929
53574
2
70000
0.7972
55804
3
75000
0.7118
53385
4
70000
0.6355
44485
NPV =
57248
SINCE NPV IS POSITIVETHE PROJECT IS NOT VIABLE AND THEREFORE SHOULD BE ACCEPTED
ANSWER :- OPTION
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.