Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Garage, Inc., has identified the following two mutually exclusive projects: Year

ID: 2709031 • Letter: G

Question

Garage, Inc., has identified the following two mutually exclusive projects:

Year

Cash Flow (A)

Cash Flow (B)

0

–$

29,700

–$

29,700

1

15,100

4,650

2

13,000

10,150

3

9,550

15,900

4

5,450

17,500

What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)

Using the IRR decision rule, which project should the company accept?

If the required return is 12 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

  

Which project will the company choose if it applies the NPV decision rule?

At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Year

Cash Flow (A)

Cash Flow (B)

0

–$

29,700

–$

29,700

1

15,100

4,650

2

13,000

10,150

3

9,550

15,900

4

5,450

17,500

Explanation / Answer

IRR

Project A = 20.14%

Project B = 18.34%

Based on IRR, project A should be chosen as it has a higher IRR compared to other project

NPV

Project A = 4406.74

Project B = 4982.18

Based on NPV, project B should be chosen as it provides a higher NPV value compared to project A

At a discount rate of 19.09%, the company will be indifferent between the two projects

Project A

Project B

Year

Cash Flow

Year

Cash Flow

0

-29700

0

-29700

1

15100

1

4650

2

13000

2

10150

3

9550

3

15900

4

5450

4

17500

Let rA be the rate of return which makes NPV of Project A equals zero. That is

-29700 + 15100/(1+rA) + 13000/(1+rA)^2 + 9550/(1+rA)^3 + 5450/(1+rA)^4   = 0

Let rA = 20%, then LHS is equal to

= -29700 + 15100/(1.20) + 13000/(1.20)^2 + 9550/(1.20)^3 + 5450/(1.20)^4

= -29700 + 15100/(1.20) + 13000/1.44 + 9550/1.728 + 5450/2.0736

= -29700 + 12583.33 + 9027.78 + 5526.62+ 2628.28

= 66.01

Let rA be equal to 21%, then LHS is equal to

= -29700 + 15100/(1.21) + 13000/(1.21)^2 + 9550/(1.21)^3 + 5450/(1.21)^4

= -29700 + 15100/1.21 + 13000/1.4641 + 9550/1.771561 + 5450/2.143589

= -29700+12479.34+8879.18+5390.73+2542..46

= -408.30

rA = 0.20 + [((66.01)*(0.20-0.21))/(-408.3-66.01)]

     =0.20 + (-0.6601/-474.31)

     = 0.20 + 0.00139

     = 0.20139   or 20.14%

Let rB be the rate of return where NPV will be zero. Then

-29700 + 4650/(1+rB) + 10150/(1+rB)^2 + 15900/(1+rB)^3 + 17500/(1+rB)^4   = 0

Let rB = 18%, then LHS will be

= -29700 + 4650/(1.18) + 10150/(1.18)^2 + 15900/(1.18)^3 + 17500/(1.18)^4

= -29700 + 4650/1.18 + 10150/1.3924 + 15900/1.643032 + 17500/1.938778

= -29700 + 3940.678 + 7289.572+9677.231+9026.305

= 233.786

Let rB = 19%, then LHS would be

= -29700 + 4650/(1.19) + 10150/(1.19)^2 + 15900/(1.19)^3 + 17500/(1.19)^4

= -29700 + 4650/1.19 + 10150/1.4161 + 15900/1.685159 + 17500/2.005339

= -29700 + 3907.563 + 7167.573 + 9435.311 + 8726.703

= -462.850

rB = 0.18 + [((233.786)*(0.18 – 0.19))/(-462.85-233.786)]

rB = 0.18 + (-2.33786/-696.636)

rB = 0.18 + 0.003356

     = 0.183356 or 18.34%

Project A

Year

0

1

2

3

4

Cash Flows

-29700

15100

13000

9550

5450

Discount Factor (1/1.12^year)

1

0.892857

0.797194

0.71178

0.635518

Discounted Flows

-29700

13482.14

10363.52

6797.501

3463.574

Net Present Value of Project A

4406.74

Project B

Year

0

1

2

3

4

Cash Flows

-29700

4650

10150

15900

17500

Discount Factor (1/1.12^year)

1

0.892857

0.797194

0.71178

0.635518

Discounted Flows

-29700

4151.786

8091.518

11317.31

11121.57

Net Present Value of Project B

4982.18

Calculation of discount rate at which the company will be indifferent between two projects

NPV of project A at 18.34%

Year

0

1

2

3

4

Cash Flows

-29700

15100

13000

9550

5450

Discount Factor (1/1.1834^year)

1

0.845023

0.714064

0.6034

0.509887

Discounted Flows

-29700

12759.84

9282.826

5762.47

2778.883

Net Present Value of Project A

884.02

NPV of project B at 20.14%

Year

0

1

2

3

4

Cash Flows

-29700

4650

10150

15900

17500

Discount Factor (1/1.2014^year)

1

0.832362

0.692827

0.576683

0.480009

Discounted Flows

-29700

3870.484

7032.193

9169.259

8400.16

Net Present Value of Project B

-1227.90

r = 0.1834 + [((884.02) * (0.1834-0.2014))/(-1227.90-884.02)]

= 0.1834 + (-15.91236/-2111.92)

= 0.1834 + 0.007535

= 0.190935 or 19.09%

Project A

Project B

Year

Cash Flow

Year

Cash Flow

0

-29700

0

-29700

1

15100

1

4650

2

13000

2

10150

3

9550

3

15900

4

5450

4

17500