Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Better Mousetraps has developed a new trap. It can go into production for an ini

ID: 2709183 • Letter: B

Question

Better Mousetraps has developed a new trap. It can go into production for an initial investment in equipment of $5.7 million. The equipment will be depreciated straight line over 6 years to a value of zero, but in fact it can be sold after 6 years for $671,000. The firm believes that working capital at each date must be maintained at a level of 10% of next year’s forecast sales. The firm estimates production costs equal to $1.80 per trap and believes that the traps can be sold for $8 each. Sales forecasts are given in the following table. The project will come to an end in 6 years., when the trap becomes technologically obsolete. The firm’s tax bracket is 35%, and the required rate of return on the project is 11%. Use the MACRS depreciation schedule.

  Year:

0

1

2

3

4

5

6

Thereafter

  Sales (millions of traps)

0

.4

.5

.7

.7

.5

.3

0

What is project NPV? (Do not round intermediate calculations. Enter your answer in millions rounded to 4 decimal places.)

By how much would NPV increase if the firm depreciated its investment using the 5-year MACRS schedule? (Do not round intermediate calculations. Enter your answer in whole dollars not in millions.)

Better Mousetraps has developed a new trap. It can go into production for an initial investment in equipment of $5.7 million. The equipment will be depreciated straight line over 6 years to a value of zero, but in fact it can be sold after 6 years for $671,000. The firm believes that working capital at each date must be maintained at a level of 10% of next year’s forecast sales. The firm estimates production costs equal to $1.80 per trap and believes that the traps can be sold for $8 each. Sales forecasts are given in the following table. The project will come to an end in 6 years., when the trap becomes technologically obsolete. The firm’s tax bracket is 35%, and the required rate of return on the project is 11%. Use the MACRS depreciation schedule.

Explanation / Answer

Net Salvage value is missing in the previous answer.

Net Salvage value = salvage value x (1-t)

= 671000 x (1-0.35)

= 436,150 or 0.43615 million

PV of net salvage value = Net Salvage value x PV Factor

= 0.43615 million x 0.5346

= 0.2332

Net Present value = NPV without salvage value + PV of salvage value

= 4.915370515 + 0.2332

=5.1486 million

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Chat Now And Get Quote