Consider the following data for Yellowstone Regional Hospital (in millions of do

ID: 2710439 • Letter: C

Question

Consider the following data for Yellowstone Regional Hospital (in millions of dollars):

Static Budget

Flexible Budget

Actual Results

Revenues

$7.0

$6.8

$6.8

Costs

$6.3

$6.3

$6.6

Profits

$0.7

$0.5

$0.2

40.

Answer all parts of the question and please label your answers clearly.

a Calculate and interpret the profit variance. (2 points)

b Calculate and interpret the revenue variance. (2 points)

c Calculate and interpret the cost variance. (2 points)

Consider the following data for Yellowstone Regional Hospital (in millions of dollars):

Static Budget

Flexible Budget

Actual Results

Revenues

$7.0

$6.8

$6.8

Costs

$6.3

$6.3

$6.6

Profits

$0.7

$0.5

$0.2

Explanation / Answer

Static Budget Flexible Budget Actual Results Variance Revenues $7.00 $6.80 $6.80 $0.00 There is no revenue variance Costs $6.30 $6.30 $6.60 ($0.30) Actual costs were higher by $0.3 million than budgeted Profits $0.70 $0.50 $0.20 ($0.30) Actual proft was lesser by $0.3 million than budgeted