On February 1, 2016, Arrow Construction Company entered into a three-year constr
ID: 2711847 • Letter: O
Question
On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2016, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent and cash collected was $2,390,000.
In 2017, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2017 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2018 after additional costs of $3,940,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2016, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent and cash collected was $2,390,000.
In 2017, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2017 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2018 after additional costs of $3,940,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Explanation / Answer
2016 2017 2018 Cost incurred during the year 2140000 2640000 3940000 Estimated Cost to complete as of year end 4140000 3810000 Billing 2640000 2890000 $ 2,890,000.00 [8420000-2640000-2890000] Cash Collected 2390000 2615000 Contract Price $ 8,420,000.00 $ 8,420,000.00 $ 8,420,000.00 Cost incurred during the year $ 2,140,000.00 $ 2,640,000.00 $ 3,940,000.00 Estimated Cost to complete as of year end $ 4,140,000.00 $ 3,810,000.00 $ - Total Estimated Cost $ 6,280,000.00 $ 6,450,000.00 $ 3,940,000.00 Estimated Gross Profit/(Loss) $ 2,140,000.00 $ 1,970,000.00 $ 4,480,000.00 (Actual for 2018 Percentage Completed = 34.08% 40.93% 100.00% (Actual Cost to date/Total Estimated Cost as of year end) Revenue Recognition (Contract Price* percetage Completed) - Revenue recognised on prior years $ 2,869,235.67 $ 577,089.91 $ 4,973,674.42 (8420000*40.93%)-2869236 Gross Profit/(Loss) $ 729,235.67 $ (2,062,910.09) $ 1,033,674.42 (Revenue Recognised-Actual Cst till date) JOURNAL ENTRIES 2016 2017 Construction in progress $ 2,140,000.00 $ 2,640,000.00 Various accounts $ 2,140,000.00 $ 2,640,000.00 To record construction costs. Accounts receivable $ 2,640,000.00 $ 2,890,000.00 Billings on construction contract $ 2,640,000.00 $ 2,890,000.00 To record progress billings. Cash $ 2,390,000.00 $ 2,615,000.00 Accounts receivable $ 2,390,000.00 $ 2,615,000.00 To record cash collections. Construction in progress (gross profit) $ 729,235.67 Cost of construction (cost incurred) $ 2,140,000.00 $ 2,640,000.00 Revenue from long-term contracts (1) $ 2,869,235.67 $ 577,089.91 Construction in progress (gross LOSS) $ 2,062,910.09 To record gross profit. EXTRACT OF BALANCE SHEET 2016 2017 Current Asset Accounts Receivable $ 2,640,000.00 $ 2,890,000.00 Construction in Progress $ 2,869,235.67 $ 2,062,910.09 Less: Billing $ (2,640,000.00) $ (2,890,000.00) Costs and profit in excess of billings $ 229,235.67 $ (827,089.91)