QUESTION 1 Use the following information to calculate the percentage expected re
ID: 2711935 • Letter: Q
Question
QUESTION 1
Use the following information to calculate the percentage expected return a portfolio that is 47.5 percent invested in 3 Doors, Inc., and the rest invested in Down Co.:
3 Dorrs, Inc.
Down Co.
Expected return
28%
5%
Standard deviation
35
11
Correlation
72
QUESTION 2
Use the following information to calculate the percentage standard deviation of a portfolio that is 61.4 percent invested in 3 Doors, Inc., and the rest invested in Down Co.:
3 Dorrs, Inc.
Down Co.
Expected return
16%
11%
Standard deviation
41
33
Correlation
0.76
3 Dorrs, Inc.
Down Co.
Expected return
28%
5%
Standard deviation
35
11
Correlation
72
Explanation / Answer
Question 1:
Expected return = 0.475 * 28% + 0.525 * 5%
= 15.925%
Question 2:
Expected standard deviation = sqrt[(0.614 * 41%)2 + (0.386 * 33%)2 + 2 * 0.76 * 0.614 * 0.386 * 41% * 33%]
= 35.82%
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.