Purple Haze Machine Shop is considering a four-year project to improve its produ
ID: 2718407 • Letter: P
Question
Purple Haze Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $470,000 is estimated to result in $190,000 in annual pretax cost savings. The press falls in the MACRS five-year class, and it will have a salvage value at the end of the project of $80,000. The press also requires an initial investment in spare parts inventory of $20,000, along with an additional $2,500 in inventory for each succeeding year of the project. The shop’s tax rate is 35 percent and its discount rate is 9 percent. Calculate the NPV for this project
Explanation / Answer
Purple Haze Machine Shop is considering a four-year project to improve its produ