I understand it, but getting the wrong adjusting entries for year end of 2015. S
ID: 2720220 • Letter: I
Question
I understand it, but getting the wrong adjusting entries for year end of 2015. Someone please help.
Finally, in addition to its normal operations, ThreeBrothers also has a division that builds university fitness centers. At the end of 2014, there was one building project in process , the $45,000,000 SoFancy University project (SFU), which was started in June 2014. The original estimated costs for the SFU project totaled $41,750,000 but there have been substantial increases in the cost of materials resulting in a current total cost estimate of $45,100,000 for the job. The contract does not allow for renegotiation of the contracted price. ThreeBrothers has a legally binding enforceable contract with both universities and all parties are expected to be able to perform under the contracts. The general ledger account Construction-in-Progress
Inventory shows the following before any 2015 year-end adjusting entries.
Here is some extra info. Income statement/ BS from 2014 and the uadj trial balance of 2015
Explanation / Answer
SFU Contract Revenue as per Contract 45,000,000 Current Cost Estimate 45,100,000 Expected Loss in Contract (100,000) Cost Incurred till2015 35,600,000 Billing done Till Date 35,000,000 % Completion = Current cost/Estimated cost= 78.9% % revenue can be recognized 35,521,064 Under billed amount 521,064 Adjusting Journal Entries Account Title Dr $ Cr$ Cost in excess of billing 600,000 Cost of contract (additional loss next year) 21,064 Sales 521,064 Loss on Contract 100,000 As the total loss from contract is known , the total loss of $ 100,000 recognized in 2015 with additional cost recorded as per recommended GAAP. Next year the actual cost will be credited by the same extra cost recoreded this year.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.