An all-equity firm is considering the following projects: The T-bill rate is 5.3
ID: 2723631 • Letter: A
Question
An all-equity firm is considering the following projects: The T-bill rate is 5.3 percent, and the expected return on the market is 12.3 percent. a. Compared with the firm's 12.3 percent cost of capital, Project W has a expected return, Project X has a expected return, Project Y has a expected return, and Project Z has a expected return. b. Project W should be Project X should be Project Y should be and Project Z should be . c. If the firm's overall cost of capital were used as a hurdle rate, Project W would be Project X would be Project Y would be and Project Z would be .Explanation / Answer
a. Expected Return = Risk Free Rate + Beta (Market Rate - Risk Free rate)
Project W = 5.30 + .65 * (12.30 - 5.30) = 9.85% , IRR = 9.50%
Project X = 5.30 + .74 * (12.30 - 5.30) = 10.48% , IRR = 10.7%
Project Y = 5.30 + 1.33 * (12.30 - 5.30) = 14.61% , IRR = 14.2%
Project Z = 5.30 + 1.44 * (12.30 - 5.30) = 15.38% , IRR = 17.3%
b. If the expected return of a project is higher than cost of capital it should be accepted. Accordingly,
Project W rejected
Project X rejected
Project Y accepted
Project Z accepted
c. A project should be accepted if the IRR exceeds hurdle rate. As per this rule, if hurdle rate is 12.3%,
Project W rejected
Project X rejected
Project Y accepted
Project Z accepted
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.