Question 29 - Assume that the manager faces a capital budget constraint with res
ID: 2725003 • Letter: Q
Question
Question 29 -
Assume that the manager faces a capital budget constraint with respect to total dollars available today to invest in new projects, $46 million. Assume same WACC for each project. All else equal, which project or set of otherwise independent projects should the manager choose and why?
Project
NPV
(in $millions)
IRR
Required Investment today
A
$ 10
14.0%
$ 22
B
$ 10
12.9%
$ 23
C
$ 11
14.1%
$ 25
Project
NPV
(in $millions)
IRR
Required Investment today
A
$ 10
14.0%
$ 22
B
$ 10
12.9%
$ 23
C
$ 11
14.1%
$ 25
Explanation / Answer
A
B
C
NPV
10
10
11
IRR
14
12.9
14.1
Rank
II
III
I
Required Investmnet
22
23
25
NPV is more relevant for decision making. Project A and B npv is same hence for ranking used IRR also ,Ranked the highest IRR first.
If we have select to Projects as per ranking we don’t have enough investment .ie For C $47 and A $22=$47
We cant even select C and B= 25+23=$48
Hence it is not possible to select projects as per ranks ,we have select A and B= $22+23=$45
A
B
C
NPV
10
10
11
IRR
14
12.9
14.1
Rank
II
III
I
Required Investmnet
22
23
25
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.