Consider a project to supply Detroit with 40,000 tons of machine screws annually
ID: 2728056 • Letter: C
Question
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,000,000 investment in threading equipment to get the project started; the project will last for six years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $300 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the six-year project life. It also estimates a salvage value of $600,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $370 per ton. The engineering department estimates you will need an initial net working capital investment of $500,000. You require a return of 15 percent and face a marginal tax rate of 30 percent on this project.
a-1 What is the estimated OCF for this project? (Do not round intermediate calculations. Round your answer to the nearest whole number, e.g., 32.)
OCF $_________
a-2 What is the estimated NPV for this project? (Do not round intermediate calculations. Round your answer to 2 decimal places, e.g., 32.16.)
NPV $____________
b. Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±15 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±5 percent. What are your worst-case and best-case NPVs for this project? (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)
Worst-case $__________
Best-case $___________
Explanation / Answer
a-1)
Calculation of Operating cash flows (OCF)
Contribution (370 - 300) * 40000
(-) Fixed costs
2800000
700000
Gross income
(-) Depreciation [5000000 - 600000] / 6
2100000
733333.33
Earnings before interest & Tax
(-) Tax @ 30 %
1366666.67
410000
Earnings after tax
(+) Depreciation
956666.67
733333.33
Conclusion:- Operating cash flow (OCF) = $ 1690000
a-2) Estimated NPV of project = Present value of cash inflow - P.V. of cash outflow
= 6870160 (ii) - 5500000 (i) = $ 1370160 (approx)
i) P.V. of cash outflow = 5000000 + 500000 = $ 5500000
ii) P.V. of Cash inflow:-
P.V. of OCF = 1690000 * Cumulative P.V. Factor for 6 Years @ 15 %
= 1690000 * 3.784
Conclusion:- Estimated NPV of project = $ 1370160.
Contribution (370 - 300) * 40000
(-) Fixed costs
2800000
700000
Gross income
(-) Depreciation [5000000 - 600000] / 6
2100000
733333.33
Earnings before interest & Tax
(-) Tax @ 30 %
1366666.67
410000
Earnings after tax
(+) Depreciation
956666.67
733333.33
Operating cash flow 1690000Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.