Find the average tune per unit required to produce the first 34 units, if the sl
ID: 2735855 • Letter: F
Question
Find the average tune per unit required to produce the first 34 units, if the slope parameter of the learning rate is 88% and first unit takes 492 hours. A. 244.291 hours per unit B. 316.142 hours per unit C. 10,749 hours per unit D. 0.643 hours per unit
Find the average tune per unit required to produce the first 34 units, if the slope parameter of the learning rate is 88% and first unit takes 492 hours. A. 244.291 hours per unit B. 316.142 hours per unit C. 10,749 hours per unit D. 0.643 hours per unit
Find the average tune per unit required to produce the first 34 units, if the slope parameter of the learning rate is 88% and first unit takes 492 hours. A. 244.291 hours per unit B. 316.142 hours per unit C. 10,749 hours per unit D. 0.643 hours per unit
Explanation / Answer
Calculate the learning curve factor = log(0.88)/log(2) = -0.18442457113.
T1 = 492 hours.
T34 = 492 * (34^-0.18442457113) = 256.7572.
Near to option A.
Therefore, the correct answer is option A.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.