Taiwan Semiconductor (TSM) is considering a 2-year project in the U.S. The proje
ID: 2736470 • Letter: T
Question
Taiwan Semiconductor (TSM) is considering a 2-year project in the U.S. The project's expected dollar cash flows consist of an initial investment of $100,000 with cash flows of $70,000 in year 1 and $60,000 in year 2. The risk-adjusted cost of capital for the project is 20%. The current exchange rate is NT$30=$1. Risk-free interest rates in the U.S. and Taiwan are:
U.S.
1-year: 4.0%
2-year: 7%
Taiwan:
1-year: 3%
2-year: 5%
What is the NPV of the project?
Note: During the calculations, the rounding of the numbers may impact the final answer. So select the closest answer.
Select one:
a. $12,532.86
b. -$63,166.67
c. -$52,900.77
d. $45,655.09
e. $23,090.74
Explanation / Answer
1. Initial investement = 100000x $NT30 = $NT3000000
2. Exchange rate after 1 year:
NT$30=$1
NT$30(1.03) = $1(1.04)
NT$29.71 = $1
Exchange rate after 2 years:
NT$29.71 = $1
NT$29.71(1.05) = $1(1.07)
NT$29.15 = $1
3. Cash flow after 1 year = 70000 x 29.71 = $NT2079700
4. Cash flow after 2 years = 60000 x 29.15 = $NT1749000
5. NPV = [2079700 x 0.833] + [1749000 x 0.694] - 3000000
NPV = $NT-53803.90
This answer is close to option c. Hence NPV is $52.900.77
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.