Given the following estimated task duration you received from expert team members, estimate the duration you will use for each of these tasks on your project schedule by incorporating the beta distribution method: Task A: optimistic 5, pessimistic 13, most likely 6 Given the following estimated task duration you recerved from expert team members, estimate the duration you will use for each of these tasks on your project schedule by incorporating the beta distribution method: Task A optimistic 5, pessimistic 13, most likely 6 Task B optimistic 7, pessimistic 15, most likely 8 O Task A: 7, Task B: 9 O Task A: 8, Task B:9 Task A. 7, Task B: 5 0 Task A: 6, Task B: 8 , las 4 Previous Next

Explanation / Answer

Answer:

According to Beta Distribution Method; Expected Value = (Optimistic + 4 x Most Likely + Pessimistic) Estimates / 6

here in the given question, the E values are;

Task A = 5 + 4x6 + 13 / 6 = 7

Task B = 7 + 4x8 + 15 / 6 = 9

Therefore, the correct option is Option A; Task A 7 and Task B 9.