Question
Given the following estimated task duration you received from expert team members, estimate the duration you will use for each of these tasks on your project schedule by incorporating the beta distribution method: Task A: optimistic 5, pessimistic 13, most likely 6 Given the following estimated task duration you recerved from expert team members, estimate the duration you will use for each of these tasks on your project schedule by incorporating the beta distribution method: Task A optimistic 5, pessimistic 13, most likely 6 Task B optimistic 7, pessimistic 15, most likely 8 O Task A: 7, Task B: 9 O Task A: 8, Task B:9 Task A. 7, Task B: 5 0 Task A: 6, Task B: 8 , las 4 Previous NextExplanation / Answer
Answer:
According to Beta Distribution Method; Expected Value = (Optimistic + 4 x Most Likely + Pessimistic) Estimates / 6
here in the given question, the E values are;
Task A = 5 + 4x6 + 13 / 6 = 7
Task B = 7 + 4x8 + 15 / 6 = 9
Therefore, the correct option is Option A; Task A 7 and Task B 9.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.