1. Project Procurement Management ________. A. Describes the processes required
ID: 2746541 • Letter: 1
Question
1. Project Procurement Management ________.
A. Describes the processes required to procure products, services, or results from outside the performing organization.
B. Involves processes to ensure that the project procures products, services, or results at the lowest possible cost.
C. Includes the processes to procure products, services, or results, but does not include the ongoing performance management of the selected seller(s).
D. Is not used by the seller of the product, service, or results under a contract.
Explanation / Answer
1. Project Procurement Management ______
A. Describes the processes required to procure products, services, or results from outside the performing organization.
REASON:When the projects get products and other services from outside the acting or performing organization,the method for procurement preparation by terms would be acted for any product or service.