For each of the problems listed, determine the following quantities for each act
ID: 2748456 • Letter: F
Question
For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.
please complete this table with the information above
For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.
Activity ImmediatePredecessor Estimated Time (days) A — 15 B A 12 C B 6 D B 5 E C 3 F — 8 G F 8 H F 9 I G 7 J H 14 K J 6 End D, E, I, K
please complete this table with the information above
Explanation / Answer
Activity Predecessor Time (days) ES EF LF LS Slack A — 15 0 15 22 7 7 B A 12 15 27 34 22 7 C B 6 27 33 40 34 7 E B 5 27 32 43 38 11 D C 3 33 36 43 40 7 F — 8 0 8 8 0 0 G F 8 8 16 16 8 0 I F 9 8 17 43 34 26 H G 7 16 23 23 16 0 J H 14 23 37 37 23 0 K J 6 37 43 43 37 0