Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A company is examining two projects as a part of its expansion plan for the next

ID: 2752684 • Letter: A

Question

A company is examining two projects as a part of its expansion plan for the next year. Both projects are not mutually exclusive. The cost of Project A is $12,950 while Project B is expected to cost $18,625. The company's cost of capital (required rate of return) is 11.5 %. Expected annual cash flows are projected to be as follows:

Year

Project A

Project B

1

3,250.00

6,850.00

2

3,250.00

6,850.00

3

3,250.00

6,850.00

4

3,250.00

6,850.00

5

3,250.00

6,850.00

Each project will last an estimated 5 years with no remaining significant scrap value. Determine the IRR and the NPV for each of these two projects. What should Henn Corp decide about each proposed project.

Year

Project A

Project B

1

3,250.00

6,850.00

2

3,250.00

6,850.00

3

3,250.00

6,850.00

4

3,250.00

6,850.00

5

3,250.00

6,850.00

Explanation / Answer

Calculation of NPV

Net Present value = Present value of cash inflows less Initial cost

Present value factor at 11.50 % for 5 years = 3.64988

So net Present value =

Project A = (3250 * 3.64988) - 12950 = -1087.89 (negative NPV)

Project B = (6850 * 3.64988) - 18625 = 6376.68

Calculation IRR

We know that at IRR the present value of cash flows = present value of inflows

Project A outflows = 12950

Project A inflows = 3250 for 5 years

So when we discount 3250 for 5 years at 8.075% interest rate we get 3250 * 3.98483 = 12950

Therefore IRR for project A is 8.077 %

Project B cash inflows = 6850 for 5 years

intial outflow = 18625

So when we discount at 24.464% 6850 for 5 years we get 6850 * 2.71911 = 18625.

Therefore IRR for project B = 24.464%

Based on NPV method Hence Henn corp Should go for project B because it has positive NPV and project A is not viable as it has negative NPV.

Also based on IRR the Henn corp should go for Project B as IRR is more then required rate of return for project B and reject project A as project A has lower IRR as compared to required rate of return.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote