Scanlin, Inc., is considering a project that will result in initial aftertax cas
ID: 2754645 • Letter: S
Question
Scanlin, Inc., is considering a project that will result in initial aftertax cash savings of $1.89 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debtequity ratio of .80, a cost of equity of 12.9 percent, and an aftertax cost of debt of 5.7 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of 1 percent to the cost of capital for such risky projects.
What is the maximum initial cost the company would be willing to pay for the project?
Scanlin, Inc., is considering a project that will result in initial aftertax cash savings of $1.89 million at the end of the first year, and these savings will grow at a rate of 2 percent per year indefinitely. The firm has a target debtequity ratio of .80, a cost of equity of 12.9 percent, and an aftertax cost of debt of 5.7 percent. The cost-saving proposal is somewhat riskier than the usual project the firm undertakes; management uses the subjective approach and applies an adjustment factor of 1 percent to the cost of capital for such risky projects.
Explanation / Answer
cost of capital:
Ratio cost weighted cost
Debt 0.8 5.7 4.56
Equity 0.2 12.9 2.58
7.14
Since company adjust the cost for risk so adjusted cost of capital is = 7.14+1= 8.14
Initial capital= cash inflows/ (cost of capital - growth rate)
Initial capital = 1,890,000/ ( 0.0814 - 0.02)
Initial capital = 30,781,759
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.