In this example, the control account manager (CAM) statuses work package 8 as of
ID: 2757092 • Letter: I
Question
In this example, the control account manager (CAM) statuses work package 8 as of end of November. Given the Earned Value Management (EVM) technique for this work package, what is the BCWP for the month of November?
Excerpt of the Engine Critical Design CAP. Work package 8 Engineering Support uses an LOE EVM technique with BCWS scheduled as follows: August $6,983; September 8,938; October 8,938; November $9,760; and December $8,938. The BAC is $43,557. Time Now is at the end of November. The current BCWS for each month is: August $6,983; September 8,938; October 8,938; November $9,760; and December $8,938. The current BCWP for each month is blank.
possible answers
$34,619 $0 $9,760 $18,698Explanation / Answer
BCWP = Sum of BCWS = 6983+ 8938+ 8938 + 9760 = 34,619.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.