2. The Z-90 project being considered by Steppingstone Inc. (SI) has an up-front
ID: 2757187 • Letter: 2
Question
2. The Z-90 project being considered by Steppingstone Inc. (SI) has an up-front cost of $250,000. The project's subsequent cash flows are critically dependent on whether another of its products, Z-45, becomes an industry standard. There is a 50% chance that the Z-45 will become the industry standard, in which case the Z-90's expected cash flows will be $110,000 at the end of each of the next 5 years. There is a 50% chance that the Z-45 will not become the industry standard, in which case the Z-90's expected cash flows will be $25,000 at the end of each of the next 5 years. Assume that the cost of capital is 12%.
Refer to Exhibit 14.4. Based on the above information, what is the Z-90's expected net present value?
A) -$6,678
B) -$3,251
C) $15,303
D) $20,004
E) $45,965
Explanation / Answer
EXPECTED INITIAL CASH FLOW IN YEAR 0 IS ($250000)
EXPECTED INBETWEEN CASH FLOW
YEAR CASH FLOW PROBABILITY EXPECTED VALUE
1-5 $110000 0.5 $55000
1-5 $25000 0.5 $12500
EXPECTED VALUE $67500
CALCULATION OF EXPECTED NPV
YEAR CASH FLOW DISCOUNTING FACTOR DISCOUNTED CASH FLOW
0 ($250000) 1.000 ($250000)
1-5 $67500 3.60478 $243322.65
EXPECTED NPV ($6677.35) APROX
ANSWER A
NOTE- THERE IS A LITTLE DIFFRENCE BECAUSE OF ROUNDING OF THE DECIMAL.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.