Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A contractor must choose between buying or renting a crane for the duration of a

ID: 2757278 • Letter: A

Question

A contractor must choose between buying or renting a crane for the duration of a 5 year construction project. The contractor uses an MARR of 8%. The crane costs $590,000 and can be sold for $350,000 after 5 years. The cost to operate and maintain the crane is $230,000 per year. Renting the crane costs $340,000 per year including all operating and maintenance costs.

A. Determine the future worth of costs (FWC) for the contractor's best option. Express your answer as a positive number is $ to the nearest $1,000.

B. Determine the incremental benefit-cost ratio that the contractor should use to decide between buying and renting. Express your answer to two decimal places.

The answer to part A is 1866222, just a good explanation. (Preferably formulas, not excel)

Not sure what part B answer is.

Explanation / Answer

NPV of Buying crane option

($)

Year

Particulars

Amount

P.V Factor @ 8%

Total

0

Initial investment

5,90,000

1

590000.00

1

operating and maintenance costs.

2,30,000

0.925925926

212962.96

2

operating and maintenance costs.

2,30,000

0.85733882

197187.93

3

operating and maintenance costs.

2,30,000

0.793832241

182581.42

4

operating and maintenance costs.

2,30,000

0.735029853

169056.87

5

operating and maintenance costs.

2,30,000

0.680583197

156534.14

5

Salvage value

-3,50,000

0.680583197

-238204.12

NPV

1270119.19

NPV of Renting crane option

($)

Year

Particulars

Amount

P.V Factor @ 8%

Total

1

operating and maintenance costs.

3,40,000

0.925925926

314814.81

2

operating and maintenance costs.

3,40,000

0.85733882

291495.20

3

operating and maintenance costs.

3,40,000

0.793832241

269902.96

4

operating and maintenance costs.

3,40,000

0.735029853

249910.15

5

operating and maintenance costs.

3,40,000

0.680583197

231398.29

NPV

1357521.41

B.

Present value of Incremental benefit

($)

Year

Particulars

Amount

P.V Factor @ 8%

Total

1

Incremental Saving in operating costs.

1,10,000

0.925925926

101851.85

2

Incremental Saving in operating costs.

1,10,000

0.85733882

94307.27

3

Incremental Saving in operating costs.

1,10,000

0.793832241

87321.55

4

Incremental Saving in operating costs.

1,10,000

0.735029853

80853.28

5

Incremental Saving in operating costs.

1,10,000

0.680583197

74864.15

5

Salvage value

3,50,000

0.680583197

238204.12

NPV

677402.22

Present value of Operating exp

($)

Year

Particulars

Amount

P.V Factor @ 8%

Total

1

Operating exps

2,30,000

0.925925926

212962.96

2

Operating exps

2,30,000

0.85733882

197187.93

3

Operating exps

2,30,000

0.793832241

182581.42

4

Operating exps

2,30,000

0.735029853

169056.87

5

Operating exps

2,30,000

0.680583197

156534.14

NPV

918323.31

B/C Ratio = Present value of benefits/Initial investment+Present value of operating and          maintenance exp.

                  = 677402.22 /5,90,000 + 918323.31

                      = 0.449109431

NPV of Buying crane option

($)

Year

Particulars

Amount

P.V Factor @ 8%

Total

0

Initial investment

5,90,000

1

590000.00

1

operating and maintenance costs.

2,30,000

0.925925926

212962.96

2

operating and maintenance costs.

2,30,000

0.85733882

197187.93

3

operating and maintenance costs.

2,30,000

0.793832241

182581.42

4

operating and maintenance costs.

2,30,000

0.735029853

169056.87

5

operating and maintenance costs.

2,30,000

0.680583197

156534.14

5

Salvage value

-3,50,000

0.680583197

-238204.12

NPV

1270119.19

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote