#1 Suppose you calculate the ordinary payback for a project, given the project c
ID: 2758093 • Letter: #
Question
#1
Suppose you calculate the ordinary payback for a project, given the project cash flows and a required rate of return of 12%. After you calculate the ordinary payback, you discover that the actual required rate of return is 14%. The new payback you calculate using a required rate of return of 14% would be
a. lower than the payback calculated with a required rate of return of 12%.
b. higher than the payback calculated with a required rate of return of 12%.
c. the same as the payback calculated with a required rate of return of 12%.
d. uncertain because it could be either lower or higher than the payback calculated with a required rate of return of 12%
a. lower than the payback calculated with a required rate of return of 12%.
b. higher than the payback calculated with a required rate of return of 12%.
c. the same as the payback calculated with a required rate of return of 12%.
d. uncertain because it could be either lower or higher than the payback calculated with a required rate of return of 12%
Explanation / Answer
The answer is,
The new pay back period calculated using the required rate of return of 14% is lower than the payback calculated with a required rate of return of 12%.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.