Your firm is contemplating the purchase of a new $1,036,000 computer-based order
ID: 2759355 • Letter: Y
Question
Your firm is contemplating the purchase of a new $1,036,000 computer-based order entry system. The system will be depreciated straight-line to zero over its 5-year life. It will be worth $100,800 at the end of that time. You will be able to reduce working capital by $140,000 (this is a one-time reduction). The tax rate is 32 percent and your required return on the project is 22 percent and your pretax cost savings are $470,250 per year. 1.)What is the NPV of this project? 2.)What is the NPV if the pretax cost savings are $338,600 per year? 3.) At what level of pretax cost savings would you be indifferent between accepting the project and not accepting it?
Explanation / Answer
INITIAL CASH FLOW
PURCHASE PRICE OF NEW EQUIPEMENT = ($1036000)
REDUCTION IN WORKING CAPITAL = $140000
TOTAL CASH FLOW = $896000
INBETWEEN CASH FLOW YEAR 1-5
PRE TAX COST SAVING = $470250
LESS TAX @ 32% = ($150480)
ADD DEPRICIATION = $207200
AFTER TAX CASHFLOW =$526970
TERMINAL CASHFLOW
SALVAGE VALUE = $100800
LESS TAX @32% = ($32256)
AFTER TAX CASH FLOW = $68544
1./
NPV OF THE PROJECT
2./
IF THE PRE TAX COST SAVING ARE $338600
INBETWEEN CASH FLOW YEAR 1-5
PRE TAX COST SAVING = $338600
LESS TAX @ 32% = ($108352)
ADD DEPRICIATION = $207200
AFTER TAX CASHFLOW =$437488
NPV OF THE PROJECT
3./
INDIFFRENCE BETWEEN ACCEPTIN & REJECTING POINT IS NPV = 0
SO LET THE PRE TAX COST SAVING BE "X"
AFTER TAX COST SAVING "X" * (1 - 0.32) + $207200
= 0.68X + $207200
NPV = ($896000) + 2.8636 * (0.68X + $207200) + $68544 * 0.3700
0 = ($896000) + 1.9472X + $593337.92 + $25361.28
1.9472X = $277300.8
X = $277300.8 / 1.9472
X = $142410.02
AT $142410.02 PRETAX COST SAVING IT WOULD BE INDIFFRENT BETWEEN ACCEPTING THE PROJECT AND NOT ACCEPTING THE PROJECT.
YEAR CASH FLOW DISCOUNTING FACTOR @22% DISCOUNTED CASHFLOW 0 ($896000) 1.000 ($896000) 1-5 $526970 2.8636 $1509031.29 5 $68544 0.3700 $25361.28 NPV $638392.57Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.