One of the four ovens at a bakery is being considered for replacement. Its salva

ID: 2762162 • Letter: O

Question

One of the four ovens at a bakery is being considered for replacement. Its salvage value and maintenance costs are given in the table below for several years. A new oven costs $80,000 and this price includes a complete guarantee of the maintenance costs for the first two years, and it covers a good proportion of the maintenance costs for years 3 and 4. The salvage value and maintenance costs are also summarized in the table below

a.Estimate the ESL for each of the ovens (old and new) if the MARR equals 10%?

b.What is the minimum AW cost for each of the ovens (old and new) ?

c.Should the old oven be replaced this year ?

Old Over Salvage Value Maintenance New Oven Salvage Value Maintenance at End of Year $20,000 17,000 14,000 11,000 7,000 Year Costs at End of Year $80,000 75,000 70,000 66,000 62,000 Costs 9,500 9,600 9,700 9,800 2 1,000 3,000 4

Explanation / Answer

Old oven -

EAC

Capital Recovery

Maintenance

S Value at (P-S) × (A/P, 10%, n) Main.

9,500 +

EAC

Year

EOP

+ Si

Costs 100(A/G, 10%, n)

Total

0

P = 20,000

1

17,000

5,000.00

9,500

9,500.00

14,500.00

2

14,000

4,857.20

9,600

9,547.60

14,404.80

3

11,000

4,718.90

9,700

9,593.70

14,312.60*

4

7,000

4,801.50

9,800

9,638.10

14,439.60

*Economic life = 3 years, with EAC = $14,312.60

New Oven -

EAC

EAC

Capital Recovery

Maintenance

S Value at (P-S) × (A/P, 10%, n) Main.

9,500 +

EAC

Year

EOP

+ Si

Costs 100(A/G, 10%, n)

Total

0

P = 80,000

1

75,000

13,000.00

0

0

13,000.00

2

70,000

12,762.00

0

0

12,762.00

3

66,000

12,229.40

1,000

302.10a

12,531.50*

4

62,000

11,879.00

3,000

883.55b

12,762.55

a 1,000(A/F, 10%, 3) = $302.10

b [1,000(F/P, 10%, 1) + 3000](A/F, 10%, 4) = $883.55

*Economic life = 3 years, with EAC = $12,531.50

Since EAC defender > EAC challenger (14,312.6 > 12,531.5) replace oven this year.

EAC

EAC

Capital Recovery

Maintenance

S Value at (P-S) × (A/P, 10%, n) Main.

9,500 +

EAC

Year

EOP

+ Si

Costs 100(A/G, 10%, n)

Total

0

P = 20,000

- - - -

1

17,000

5,000.00

9,500

9,500.00

14,500.00

2

14,000

4,857.20

9,600

9,547.60

14,404.80

3

11,000

4,718.90

9,700

9,593.70

14,312.60*

4

7,000

4,801.50

9,800

9,638.10

14,439.60

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at drjack9650@gmail.com
Chat Now And Get Quote