You are considering two independent projects that have differing requirements. P
ID: 2769114 • Letter: Y
Question
You are considering two independent projects that have differing requirements. Project A has a required return of 12 percent compared to Project B’s required return of 13.5 percent. Project A costs $75,000 and has cash flows of $21,000, $49,000, and $12,000 for Years 1 to 3, respectively. Project B has an initial cost of $70,000 and cash flows of $15,000, $18,000, and $41,000 for Years 1 to 3, respectively. Given this information, you should: 1. accept both Project A and Project B. 2. accept Project A and reject Project B. 3. accept Project B and reject Project A. 4. reject both Project A and Project B. 5. accept whichever one you want but not both.
Explanation / Answer
Project A initial cost=$ 75000 required rate=12% cash flow y1 $ 21000 y2 $ 49000 y3 $ 12000
NPV= -75000+21000(0.893)+49000(0.797)+12000(0.712)
-75000+18753+39053+8544
-75000+66350= -8650
Project B Initial cost =$ 70000 RR=13.50 cash flow 1 y=$ 15000 y2=$ 18000 y3= $ 41000
NPV -70000+15000(0.8811)+18000(0.7763)+41000(0.6839)
-70000+13216.50+13973.40+28039.90
-70000+55229.80=-14770.20
4) reject both project A and B
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.