A firm wishes to bid on a contract that is expected to yieldthe following after-
ID: 2771034 • Letter: A
Question
A firm wishes to bid on a contract that is expected to yieldthe following after-tax net cash flows at the end of eachyear: year netcash flow 1 $5,000 2 $8,000 3 $9,000 4 $8,000 5 $8,000 6 $5,000 7 $3,000 8 $-1,500 To secure the contract, the firm must spend $30,000 to retoolits plant. This retooling will have no salvage value at theend of the eight years. Comparable investment alternativesare available to the firm that earn 12 percent compoundedannually. The depreciation tax benefit from the retooling isreflected in the net cash flows in the table. a) compute the project's net present value. b) should the project be adopted? c) what is the meaning of the computed net present valuefigure? A firm wishes to bid on a contract that is expected to yieldthe following after-tax net cash flows at the end of eachyear: year netcash flow 1 $5,000 2 $8,000 3 $9,000 4 $8,000 5 $8,000 6 $5,000 7 $3,000 8 $-1,500 To secure the contract, the firm must spend $30,000 to retoolits plant. This retooling will have no salvage value at theend of the eight years. Comparable investment alternativesare available to the firm that earn 12 percent compoundedannually. The depreciation tax benefit from the retooling isreflected in the net cash flows in the table. a) compute the project's net present value. b) should the project be adopted? c) what is the meaning of the computed net present valuefigure?Explanation / Answer
Year
Cash Inflows
PV Factor at 12%
Net Present Value
Net Present Value
(a) Calculating NetPresent Value (NPV):Year
Cash Inflows
PV Factor at 12%
Net Present Value
0 ($30,000.00) 1 ($30,000.00) 1 $5,000.00 0.8929 $4,464.50 2 $8,000.00 0.7972 $6,377.60 3 $9,000.00 0.7118 $6,406.20 4 $8,000.00 0.6355 $5,084.00 5 $8,000.00 0.5674 $4,539.20 6 $5,000.00 0.5066 $2,533.00 7 $3,000.00 0.4523 $1,356.90 8 ($1,500.00) 0.4039 ($605.85)Net Present Value
$155.55 (b) Here the Project has Positive NetPresent Value (NPV). Thus, the Project should be accepted. (c ) Computed NPV is the Present Valueof an investment's future net cash flows minus the initialinvestment. If the NPV is positive, the investment should beaccepted otherwise it shouldbe rejected.Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.